Draft Energy Bill: Pre-legislative Scrutiny - Energy and Climate Change Contents


4  Investment Instruments

147.  The White Paper stressed the need for clarity and certainty to engender investor confidence. But it also recognised that changes to the market under EMR could lead to some investment decisions being delayed because they are planned to be taken before the introduction of CfDs in 2014.[170]

148.  Chapter 2 (Clauses 14-19) of the draft Bill provides for the Secretary of State to issue "investment instruments" in order to prevent investment decisions being delayed by the EMR process. The instruments will in effect be as binding as the forthcoming CfD regime and seek to avoid a hiatus by providing "certainty for developers on the revenue stream that will be forthcoming".[171]

149.  DECC will enter into discussions with developers whose projects meet certain criteria (including timing, and ineligibility for support under the RO). [172] A range of "Final Investment Decision [FID]-enabling products" may be used varying from letters of comfort to an issue of a CfDs once powers exist; to be determined on a case by case basis. [173] The negotiation process may produce binding arrangements on the terms of the CfD, including the contract duration, risk allocation, strike price and financeability.[174]

150.  The main focus of the debate on investment instruments has been the plan for a new nuclear power plant, Hinkley Point C. EDF said:

EDF Energy and our co-investor Centrica have recently started discussions with DECC on Final Investment Decision (FID) Enabling to support our project at Hinkley Point C. It is important that this process is conducted in a timely manner and results in a legally binding agreement. [175]

151.  As with the general debate on setting the strike price for nuclear (see paragraphs 131-134), many witnesses expressed concern that there was a lack of transparency and accountability in the investment instrument negotiations for Hinkley C[176]. EDF and Centrica have sent in their letter of eligibility for Hinkley C, so the negotiations "have not really started" although the next step is how to arrive at a strike price.[177] EDF assured us that there would be openness and transparency in the process and that the outcome would be "as good as if there was an auction".[178] RWE npower (who are trying to sell their Horizon Nuclear Power project) were not convinced and wanted to see more transparency around the Hinkley C project.[179] Given that EDF and Centrica was the first project to be put forward for consideration, RWE wanted transparency around the terms and conditions offered, so that subsequent projects were not disadvantaged.[180]

152.  SSE argued that if an investment instrument was provided to a nuclear developer, it would be hard to see how it would not be challenged by the Commission as state aid.[181] However, EDF were not perturbed and told us that the "principle of the transitional arrangements is to make early investment possible, for which there is a strong case. It is simply a practical arrangement with, we believe, no bias and therefore no State Aid implications".[182]

153.  We share the concerns of many witnesses about the transparency of the FID-enabling process. Hinkley C is the first project to be considered under the process. We recommend that DECC ensures that any contract terms agreed are published as soon as possible. We also recommend that, as with setting strike prices under the CfD mechanism, an independent panel of experts should be appointed to oversee the investment instrument negotiations, and should report to Parliament on value for money for consumers (see paragraph 134).

154.  Under Clause 14 an investment instrument may provide for payments based on a strike price and a market reference price and include such provision as the Secretary of State considers necessary or desirable and, in particular, provision about various matters listed in clause 14(6) and covering the same areas as those to be covered in provisions included in a CfD. The draft Bill provides for investment instruments to be issued during the passage of the legislation and, if they comply with certain conditions including being laid before Parliament, puts a duty on the Secretary of State to issue the instruments after the Bill is enacted.[183] Clause 16 provides for a similar process for the issuing of instruments between the Bill's enactment and the end of 2015.

155.  Although Clause 19 does provide for further provision to be made in regulations about investment instruments (and those regulations will be subject to the negative procedure), there is no provision for formal Parliamentary scrutiny of investment instruments (no negative or affirmative procedures), beyond the requirement for the instruments to be laid. The implication is that instruments which may form a key aspect of the development of the electricity market until at least the end of 2015, will not be subject to the same level of Parliamentary scrutiny as those made through CfD regulations (which will be negative procedure), after the Bill becomes an Act. This may lead to concerns over a lack of transparency and Parliamentary control.


170   DECC, Planning our electric future: a White Paper for secure, affordable and low-carbon electricity, CM 8099, July 2011p 37; DECC, Electricity market reform: policy overview, Annex B, Feed-in tariff with contracts for difference: draft operational framework, May 2012 Back

171   Draft Energy Bill, CM 8362, May 2012, Explanatory Notes, pp 199-200, paras 39-40 Back

172   DECC, Planning our electric future: technical update, December 2011, p 38 Back

173   DECC, Electricity Market Reform (EMR): Final Investment Decision (FID) Enabling, Impact Assessment, IA No: DECC0083, 16 April 2012 Fig. 3, p 13 Back

174   DECC, Electricity Market Reform (EMR): Final Investment Decision (FID) Enabling, Impact Assessment, IA No: DECC0083, 16 April 2012 p 7 Back

175   Ev 161 Back

176   Ev 123, Ev 137, Ev 151, Ev w37, Ev w71, Ev w74, Ev 187, Ev w112 Back

177   Q 51 [Mr Sambhi] Back

178   Qq 51-52 [Mr Sambhi and Mr de Rivaz] Back

179   Ev 178; In 2009 RWE npower formed a joint venture with E.ON UK called Horizon Nuclear Power to explore the possibility of developing new nuclear power station in the UK Back

180   Q 52 [Mr McElroy] Back

181   Ev 151 Back

182   Ev 161 Back

183   Clause 15 imposes a duty on the Secretary of state to issue investment instrument if it has been laid before Parliament in the period between introduction of the Bill and Royal Assent (together with a statement containing specific information see Clause 15(2)) and that and that the consent of the relevant generator/supplier was given.  Back


 
previous page contents next page


© Parliamentary copyright 2012
Prepared 23 July 2012