3 Contracts for Difference
71. Three designs of feed in tariff (FiT) were
initially considered by the Government as a replacement for the
Renewables Obligation (RO):
- a Fixed-FiT (which would pay a
fixed payment that generators receive instead of revenues
from selling electricity in the market);
- a Premium FiT (PFiT) (which would pay a fixed
premium on top of the variable wholesale electricity price); and
- a FiT with Contract for Difference (CfD) (which
would provide a long term contract set at a fixed level where
variable payments are made to ensure the generator receives the
agreed tariff and where the generator would return money to consumers
if electricity prices are higher than the agreed tariff).
72. The consultation published in December 2010
focused on the PFiT and CfD options and the White Paper put forward
a CfD as the preferred choice. Clause 1 of the draft Bill enables
the Secretary of State to make regulations about Contracts for
Difference (CfDs). [65]
However, not all witnesses were convinced that DECC had made the
right decision. Professor Catherine Mitchell (along with many
environmental NGOs) advocated scrapping CfDs in favour of a Fixed-FiT.[66]
Climatechangematters claimed that a Fixed FiT "would provide
certainty, simplicity and much better value for money".[67]
SSE preferred a PFiT, which, in its view, was "simple, understandable
and bankable". However, EDF warned that a PFiT could generate
excessive profits for generators.[68]
73. Nevertheless, there was a widespread view
that CfD as a concept has attractions, most notably, the principle
of revenue certainty provided by a long-term contract.[69]
Nor is the concept "difficult"; energy companies are
used to dealing with different regimes internationally, and CfDs
are used in Denmark and were used in Britain's previous electricity
market Pool arrangements.[70]
74. Yet the implementing arrangements proposed
have become increasingly complex, arguably to the extent of being
unworkable.[71]
Witnesses argued that the reforms could be made to work, and that
there was considerable willingness to do this, more so than for
ditching CfDs altogether (see also paragraph 16). But the proposals
as they stand in the draft Bill:
- Are not "bankable"
because a multiparty counterparty
arrangement may be neither legally enforceable, nor creditworthy,
and could require companies to post collateral and possibly be
exposed to balance sheet fluctuations;
- Introduce unacceptable levels of risk
because of the possible effect of 'rationing' under the Treasury's
levy cap and a future move towards auctions affecting access to
contracts;
- Could result in a more concentrated market
because independents and smaller-scale generators will be squeezed
out and be unable to find routes to market;
- Are overly complex,
because they are trying to cover too many disparate technologies.
Counterparty model
75. The Secretary of State helpfully clarified
that there are three different models of counterparty referred
to in the debate:
- a single counterparty with liabilities
underwritten by government;
- a multiparty counterparty arrangement, comprising
suppliers; and
- a single central counterparty organisation of
new design, which is reliant on the payment flows between suppliers
and their customers (and which is not underwritten by government).
[72]
THE SHIFT FROM A SINGLE COUNTERPARTY
UNDERWRITTEN BY GOVERNMENT TO MULTIPARTY COUNTERPARTY MODEL
76. One of the most fundamental questions about
the design of CfDs is where the liability for payments will ultimately
sit. The 2010 EMR Consultation's Impact Assessment and July 2011
White Paper's EMR Impact Assessment both suggested that under
the CfD, the risk would be borne by Government. For example, Table
4 of the White Paper Impact Assessment shows the price risk being
borne by Government balance sheets under a CfD model.[73]
The 2010 Assessment stated:
Fixed payments, premium payments and CFD provide
a relatively high degree of policy certainty for investors as
they would take the form of a contract between Government and
industry. [74]
(emphasis added)
The 2011 EMR White Paper impact assessment had this
to say about the advantage of Contracts for Difference over Premium
FiTs:
A FiT CfD,
. insulates generators and consumers
from both short-term volatility and the impacts of long-term price
trends; higher- or lower-than expected gas prices have no effect
on price received by the generator or bills paid by consumers.
This means that consumers will be shielded from longer-term wholesale
price increases, but also that they will not gain from longer-term
wholesale price decreases. Changes in wholesale prices only affect
the amount of support paid out by Government; hence the price
risk is borne by Government balance sheets.[75]
77. However, the draft Bill published in May
2012 proposed instead a "multiparty" payment model whereby
liabilities would be borne collectively by all energy suppliers.[76]
DECC claimed that in fact, it had never been the intention that
Government would act as the counterparty, and told us:
When you look at the description in the White Paper,
what we always envisaged would happen was the payments would always
flow from suppliers through to generators to make the CfD whole.
I don't think anyone really thought we would be talking about
tax money or Treasury money being used to pay out these contracts.[77]
78. While no-one would have expected the Government
to be paying these contracts, witnesses had understood
that the Government would underwrite them.[78]
In fact, we understand that DECC's messaging to the investment
community when the White Paper was published indicated that the
Government would be underwriting the liabilities and we did not
come across any witnesses who had not believed that this would
be the case. John McElroy (RWE npower) outlined:[79]
I would have to say clearly the original consultation
and what was set out in that with regards to the Contract for
Difference was quite important in the sense that the Government
as the counterparty underwriting the contract in some way and
the nature of the risks associated with these large low carbon
projects, that we saw Government's role in this as important in
terms of reducing the cost of capital. Now that Government seems
to be trying to push its involvement in these contracts away from
itself, partly driven by Treasury constraints, partly driven by
the State aid rules, inevitably that claimed cost of capital benefit
is not there.[80]
79. DECC's claim to us that "in the [White
Paper's] Impact Assessment the drafting was a little bit unfortunate"
therefore appears to be disingenuous to say the least.[81]
We find it impossible to believe that this "unfortunate drafting"
does not in fact represent a policy shift. We suspect that this
is the hand of HM Treasury at work, but its outright refusal to
co-operate with our inquiry means we have not been able to explore
the dynamic between HM Treasury's balance sheet concerns and its
deficit reduction priorities and DECC's policy objectives.[82]
DECC'S CURRENT PROPOSAL (A MULTIPARTY
COUNTERPARTY)
80. The draft Bill published in May 2012 proposed
a "multiparty payment model" whereby liabilities were
borne collectively by all energy suppliers.[83]
The CfD would be an instrument created by statute that set out
obligations on the generator on one side, and on all licensed
suppliers on the other side. The payment model would run in a
similar way to the existing Balancing and Settlement Code with
a settling agent such as Elexon to invoice generators and suppliers.
Regular but variable payments would flow to and from generators
and suppliers and in both directions.
Figure 1: The multiparty payment model

81. None of the evidence received for this inquiry
suggested that the draft Bill's proposed "multiparty contract"
(termed a "synthetic" or "virtual" counterparty
by some) would work in practice.[84]
Three major problems were identified with the proposal: that it
might not be legally enforceable, that it might not be creditworthy,
and that it would have a negative impact on suppliers' balance
sheets.
Is it legal?
82. The proposed structure has no clear legal
precedent and witnesses argued that in the case of a contractual
dispute, it was not clear with whom generators would engage to
resolve the dispute.[85]
Several witnesses had seen legal advice that a contract with a
synthetic or virtual counterparty would be legally unenforceable
and for this reason, the model was considered to be uninvestable.
[86]
Is it creditworthy?
83. Witnesses told us that it was difficult to
assess how creditworthy a "synthetic" counterparty was.[87]
The CBI said:
The current approach is different from what was anticipated
at the beginning of the EMR process, when it was thought that
Government would underpin the contracts, meaning the liability
would ultimately sit with an entity with an AAA credit rating.
Under the current model, where the liability would sit collectively
with suppliers, it is not clear what the effect on the cost of
capital would be.[88]
84. The Minister has subsequently told us:
We understand some stakeholders have said that Government
signing contracts would reduce credit risk, but given that payments
ultimately flow from suppliers to generators, the credit risk
in the scheme should reflect the robust financial health of the
UK electricity market and form a solid base for investment.
The Government aims to provide investors with a system
with a level of certainty equivalent to a contract with a counterparty
that has a strong credit rating, not that Government would be
the counterparty. Our intention was not for Government to be signing
contracts but for a credit worthy investable system.[89]
What are the implications for suppliers?
85. There is uncertainty about the accounting
treatment of CfDs and in particular, whether they might be classed
as "derivatives" (financial instruments that involve
making defeasible payments under contract).[90]
If this is the case, the long term liability for CfDs may need
to be "marked to market", that is, shown on suppliers'
profit and loss accounts. This, in turn, may have implications
for credit ratings. DECC has not yet received a definitive view
on this from the large accountancy firms.[91]
Some of the large, vertically integrated energy companies expressed
concerns about this introducing volatility into their balance
sheets that might make their investors nervous.[92]
However, E-ON had received limited reassurance on that point:
The derivative point is a real worry and I would
share the concerns already expressed on that. It is important
that the contract, whatever it is, is not viewed as a derivative.
We have had some good news on that in that if it is attached to
a particular asset then it is less likely that it will be viewed
as such.[93]
86. A further concern for suppliers was the potential
requirement to post collateral. Small suppliers in particular
were worried about this point and argued that it would not be
feasible for small organisations to do this. Good Energy told
us:
It is quite evident that there are concerns about
having a large volume of cash linked to a day-ahead price going
to your balance sheet. As a small supplier, that has impact in
terms of credit and you also have to consider the collateral requirements
... It is one of those areas that we think needs a lot more investigation.
The most recent impact assessment that we have seen, and I think
it is publicly available, is from July 2011, and there is no mention
of small suppliers in there. [94]
87. Ecotricity said that the risk to small suppliers
was "massive" in terms of the collateral required, given
that even the large energy companies had concerns about effects
on their credit ratings. They called for a 250,000 customer threshold
if these proposals were taken forward, to prevent barriers to
entry to the market.[95]
This would be similar in effect to proposals already implemented
by DECC to exempt suppliers with under 250,000 customers from
liability for levies. Independent suppliers agreed that DECC's
proposals to look at shorter arrears periods would lessen but
not remove the burden.[96]
Ofgem shares concerns about the potential impact of increased
credit and collateral requirements on small suppliers and the
risks to new entry, despite DECC's reassurances in the "Policy
Overview".[97] We
consider that suggestions that small suppliers might be exempted
partially or wholly from obligations to post collateral have merit
and recommend that the Government takes steps to ensure that small
suppliers are not disadvantaged.
Other concerns
88. In addition to these three problems, SSE
identified a further difficulty with the multiparty contract model,
relating to the potential for miscalculation of subsidy collection.
It said:
Suppliers will have to collect money in advance from
consumers to pay these contracts. Suppliers may get this wrong
and over or under collect, with huge financial implications for
them and consumers. This is a large threat for all suppliers and
a huge additional barrier to new retail market entrants.[98]
THE THIRD WAY: A SINGLE COUNTERPARTY
WITHOUT GOVERNMENT UNDERWRITING
89. The evidence suggests very strongly to us
that the multiparty proposal is not workable.[99]
Centrica and EDF supported an alternative simpler bilateral
model with a creditworthy counterparty.[100]A
recent document from DECC confirms that an "Alternative Model"
with a central counterparty is now under discussion.[101]
There would be a newly created central body that would sign bilateral
contracts with generators. It could be Government or privately-owned.
It would collect payments from suppliers, and the obligation on
suppliers would require them to post collateral to cover any liabilities
in a given period. Crucially, however, the single counterparty
would not be underwritten by Government. Key issues under
consideration include the impact of the obligation on suppliers,
administratively and financially. [102]
Figure 2: The Alternative (central, single)
Counterparty Model
90. It seems to us that the main difference between
these two models is that in one the counterparty body signs contracts
with generators, so addressing the legal signatory issues. It
certainly does not change the underwriting issue.
91. National Grid felt that the current debate
was between a multiparty counterparty and "a thin-balance-sheet
sole counterparty, effectively, which would be set up in some
convenient way", akin to the settlement role established
in 1989 for Elexon.[103]
It is "doing work with DECC to understand how you might structure
such an organisation" including checking that no unexpected
issues might arise.[104]
92. The Secretary of State told us that the model
put forward by many in the industry for a singleparty counterparty
model without Government underwriting was unproblematic.[105]
93. While many witnesses were aware that an "alternative
model" was under consideration, the novelty of this proposal
meant that considered input to our inquiry about its merits and
drawbacks was limited. We also suspect that some stakeholders
have mistakenly interpreted the new single counterparty model
to be one that is underwritten by Government.
94. We recommend that the Government
abandons the multiparty concept and reverts to a single counterparty
payment model, with a contract and counterparty design that is
legally enforceable.
95. The main purpose of the
reforms was to reduce the cost of capital for investors. The nature
of the counterparty will affect the cost of capital (see paragraph
97). In our view, a counterparty model that is underwritten by
Government would be the best way to instil investor confidence
and reduce financing costs.
96. DECC must fully assess the
implications of a single counterparty without government underwriting
on suppliers' balance sheets and on the cost of capital before
adoption of this model. This should include an assessment of what
impact this model would have on smaller suppliers to ensure that
this counterparty model would not threaten the viability of these
businesses.
THE NEED FOR A MORE RIGOROUS IMPACT
ASSESSMENT
97. The Impact Assessment published alongside
the White Paper in 2011 concluded that financing costs under a
CfD would be £2.5 billion lower than under a Premium Feed-in
Tariff. Numerous witnesses told us that this calculation was no
longer valid, since it was based on the assumption that the Government
would be the counterparty, whereas the draft Bill now suggests
the "multiparty contract" model. The Combined Heat and
Power Association explained why this was relevant: "the Government,
as counterparty would have had a top AAA credit rating, but a
different counterparty may not have such a high rating. A lower
than AAA rating would increase credit risk for investors and,
therefore, the cost of capital".[106]
98. However, DECC told us that in fact, the Impact
Assessment was based on the impact of removing the volatility
in the revenue streams, and did not take account of the nature
of the counterparty. The Secretary of State said that the "numbers
from the impact assessment would not have been different"
under a Government-underwritten or a multiparty contract model.
[107]
The Minister subsequently told us:
The Impact Assessment would not [
] need re-working,
in order to analyse an alternative payment model, because the
choice of counterparty doesn't impact on its underpinning assumptions
- which for the counterparty would be the same in either scenario.
However, we will of course produce an updated Impact Assessment
when we introduce the Bill.[108]
99. We believe that the nature
of the counterparty will have an impact on the cost of capital.
DECC's claim that the nature of the counterparty would not affect
the outcome of the Impact Assessment (IA) merely reflects the
lack of sophistication in the original assessment, rather than
the likely real-world impact on the cost of capital.
100. The Low Carbon Finance Group has questioned
the broader assumptions underpinning the Impact Assessment and
has suggested that the results reflect a "theoretical approach
to capital pricing, not how banks and investors allocate capital
to, or price capital, for various investment opportunities".[109]
101. Investors also highlighted wider concerns
about the direct impact of political and policy uncertainty on
market perceptions of risk (for example, the changes to the counterparty
arrangements and the interaction between the levy control framework
and the CfD). The draft Bill and associated documents fail to
properly assess the cumulative impact of policy changes and pronouncements
on cost of capital. We return to this in paragraphs 229 - 231.
102. DECC must update its methodology
as well as the figures when revising the Impact Assessment (IA).
The model needs to reflect real world approaches to capital pricing
and should incorporate the impact of new risks on the cost of
capital (including counterparty risk, development risk, risks
to credit ratings and basis risk). The IA should specifically
address the issue of how Government-underwriting (or lack thereof)
of the CfD counterparty affects investor risks and costs.
Allocation of CfDs: the Levy
Control Framework and use of auctions
IMPACT OF HM TREASURY'S LEVY CONTROL
FRAMEWORK
103. CfDs will fall under a cap, introduced in
the 2010 Spending Review, on DECC levy-funded spending. Deficit
neutral DECC policies that are classified by the Office of National
Statistics as tax and spend are included in the cap. HM Treasury's
Levy Control Framework (LCF) already sets spending limits to 2014/15
for the RO, Feed in Tariffs, and the Warm Home Discount.
[110] The Framework
says that if forecast or out-turn spend for any policy varies
beyond a 20% "headroom" of the cap, DECC must urgently
develop plans for bringing them back into line - or the Treasury
may seek a financial contribution.[111]
104. The draft Bill states "The Government
is minded to instruct the System Operator to only issue CfDs for
low-carbon generation up to the value of the amount set out in
the Levy Control Framework. The same principle will also apply
when the Secretary of State is issuing any investment instruments
in relation to projects that require final investment decisions
in advance of EMR implementation, and when issuing any CfDs after
the CfD regulations come into force".[112]
105. Clause 8 of the draft Bill provides for
the Secretary of State, by Order subject to parliamentary approval,
to set out the maximum cost for the scheme by setting a financial
cap on the scope of the national system operator to issue CfDs.
It also provides for a power to direct the system operator "not
to issue CFDs if the Secretary of State determines that doing
so would exceed the cost cap".[113]
106. Witnesses argued that rationing CfDs to
fit within a levy cap would introduce a new risk to developers,
who could not be sure that they would be able to secure a CfD
for an otherwise fully consented project.[114]
The Low Carbon Finance Group told us that certainty over the allocation
process would be central to the ability of developers to bring
forward a project for financing and that "at present this
is one of the weakest parts of the package".[115]
Keith Anderson (Scottish Power) said:
The concern for us would be that once we start investing
[
] on a large offshore project where I am likely to have
put at risk £100 million to £150 million to get it there
and then I get to FID [Final Investment Decision] and I do not
know if I am going to get a contract or not, that is an unacceptable
risk. So there needs to be enough transparency of how that levy
control works and where we are against it all the way through
that investment process and we would want enough flexibility in
the way it is moved to say, "By the time we get to FID bring
forward your project and look for the contract", you are
not going to get told, "Wait 18 months because there is no
money left". That would be absolutely unacceptable.[116]
107. Shaun Kingsbury (Low Carbon Finance Group)
noted that there were also risks with offering contracts too early
in the development process and suggested that a balance between
the two extremes needed to be found:
If you say up-front to anyone with even an idea of
a wind farm, "Please apply for a CfD", you may get 20
or 30 GW of applications. This is what happened, for example,
in Turkey. If you wait until the very end, then people will not
invest the capital to get there because of the risk.[117]
108. Witnesses suggested that one way of dealing
with this problem would be to introduce a pre-registration process
that could provide greater security that a contract will be awarded
earlier in the project development process.[118]
Gaynor Hartnell (Renewable Energy Association) said:
What we think is important is that a project developer
can essentially reserve a CfD at the point of winning planning
permission; for example, they might have an option to take it
up for, say, 18 months or a couple of years, by which time they
take that project to the point of the making the final investment
decision. Then the contract kicks in, and then they have a certain
period of time in which to build it. It seems to us essential
that that happens to de-risk the process. Obviously you can't
hold on to that allocation of a CfD or future allocation indefinitely,
because you would have funding sterilised by, say, a project that
was not going to reach fruition, so that is why we are suggesting,
say, 18 months or two years to take it to the financial investment
decision.[119]
109. Rationing the number of
CfDs under the levy cap increases development risk. We recommend
that DECC introduces a two-step or pre-registration process to
give developers greater confidence that they will be able to obtain
a CfD before reaching Final Investment Decision.
110. Two further problems with the levy cap were
identified: first, the fact that early projects brought through
under investment instruments (Chapter 4) might use up the pot
of CfDs before other projects were able to apply. Second, that
large scale projects like nuclear and offshore wind are "chunky"
investments and may use up an annual allocation in one go, leaving
other projects that year without CfDs.[120]
111. Suggested options for dealing with these
included improving flexibility between each year's allocation
of CfDs, a longer term (multi-year) approach, and specifying in
advance how many CfDs will be available for each type of technology
each year.[121]
112. A recent letter to us from the Minister
of State has outlined further how the Levy Control Framework (LCF)
will operate. It says that the agent allocating contracts will,
in principle, have limited discretion over who should be allocated
contracts and that precise allocation arrangements will depend
on the "affordability within the LCF", with legal obligations
being fully taken into account.[122]
Continuing RO payments and possibly other levies such as
ECO will come within the Levy Control Framework. The
Government should clarify what will be defined as falling within
the Levy Control Framework at an early date.
113. It is essential that the
Government makes clear how choices will be made by the agent allocating
contracts, in particular in allocation between technologies. We
recommend that reporting against the delivery plan should include
details of commitments already entered into at FIDs or during
FID-enabling discussions, and is transparent to other players
in order to assist long term planning.
114. Dr Kennedy (Committee on Climate Change)
told us:
We know what that [the Levy Control Framework] is
out to 2015, but it is important to understand what that is going
out beyond 2015 to 2020. We need to see a high-level number that
is commensurate with the required power sector decarbonisation
in 2020 sooner rather than later, and we need to see some flexibility
in that number, given the huge range of uncertainties around the
kind of support that might be required.[123]
115. The Committee on Climate Change has recently
recommended that a funding envelope of around £8 billion
in 2020 should be agreed now, with flexibility of +/-20-25% depending
on gas prices and low carbon technology costs.[124]
We recommend
that in order to provide greater confidence to developers, Government
should set out
a) the level of the funding
that will be available under the Levy Control Framework until
2020
b) whether the present rules
on headroom will remain as they are or will be amended to provide
more flexibility for levy allocation over the next spending period;
and
c) whether the present mechanism
of capping expenditure annually and longitudinally by line will
be maintained or relaxed during the next spending period.
We note the Committee on Climate
Change's suggestion that funding available under the Levy Control
Framework until 2020 should be around £8 billion in 2020.
USE OF AUCTIONS
116. DECC's current proposals envisage moving
to competitive CfD allocation processes, such as tenders or auctions,
as early as 2017 for some technologies.[125]
Many witnesses thought that this date was too early.[126]
Some witnesses were opposed to the use of auctions at all, suggesting
that it would introduce a similar type of development risk to
the levy cap, and thus increase the cost of finance. [127]
RenewableUK said:
Introducing auctions discourages investment because
there is less certainty to investors that their projects will
receive a contract, and at what price. This will discourage investment
in development and slow down the rate at which renewable projects
come forward.[128]
117. An additional problem with auctions is that
they do not guarantee a cheaper outcome for consumers.
Auctions may
be useful but they are not the only means to secure cost reduction.
We recommend that DECC should learn from experiences overseas
and consider setting out a planned reduction pathway for strike
prices. This would guarantee a reduction in the level of subsidy
paid by consumers over time.[129]
Ensuring routes to market
118. The third major problem identified with
the current CfD proposals is whether independent generators would
still be able to sell their electricity under the new arrangements.
Low levels of liquidity in the market mean that it is difficult
for smaller and independent generators to sell directly into the
market (for example via the power exchanges). Instead, smaller
generators often sign long-term contracts called Power Purchase
Agreements (PPAs), usually with large vertically integrated energy
suppliers. Through these, independents sell power at a discount
to market rates; they receive less for their energy because they
are reducing their risk through having longer term contracts.
PPAs are important for smaller generators who do not have a large
in-house trading capacity, and for intermittent generators who
cannot produce electricity on demand in the same way as a traditional
generator.[130] Vertically
integrated businesses, in contrast, are not reliant on PPAs because
they are able to hedge risks between the generation and supply
parts of their business.
119. The Renewables Obligation (RO) provided
an incentive for larger suppliers to enter into PPAs, but the
CfD proposals do not. In the absence of an obligation, PPAs might
only be available at a steep discount - leading to a concern that
the price received under any future PPAs will be significantly
below market price.[131]
In CfD terms, this means independent generators would not be able
to achieve the "reference" price, leaving them with
lower returns than the bigger players. Gordon MacDougall of Renewable
Energy Systems told us:[132]
One thing in terms of maintaining the RO, which seems
to be lost, is that the RO was more than just a certificate system.
It was a physical obligation on the suppliers to source the right
kind of energy and that has been lost in all of this. I think
that is a much more significant departure than many people seem
to recognise because one of the big problems with a CfD is there
is not sufficient liquidity in the market for independent generators
to trade and, as such, they require a PPA. Without the obligation
on the supply companies, there is no incentive for them whatsoever
to offer sensible PPAs to make these projects bankable.
120. The absence of "bankable" PPAs
could mean that independents will struggle to raise finance for
new projects. Ian Temperton (Climate Change Capital) told us that
"people wanting third-party finance will need Power Purchase
Agreements. They will need to give their financiers a surety that
their product is going to get into the market".[133]
121. Annex B of the EMR policy overview states
that Government "believes suppliers and independent aggregators
will continue to offer PPAs as there will be commercial opportunities
for doing so".[134]
Witnesses were sceptical about this idea, suggesting that historical
precedents were not promising.[135]
For example, the NETA trading arrangements that were introduced
in the 2001 were expected to encourage aggregators, but in practice
delivered vertical integration.[136]
The Renewable Energy Association told us "they [aggregators]
will only enter the market if there is some margin that they can
earn. There is none".[137]
RES argued that the existence or not of aggregators was "wholly
missing the point" because "the question is not whether
or not PPAs will be offered, but it is whether the PPAs will be
viable or not".[138]
122. RES warned that failure to resolve this
issue could lead to the pipeline of new renewable energy projects
drying up. It said:
If there is not an effective route-to-market available
by mid 2015, the market for independent renewable generators will
come to a halt, with independents being unable to progress projects
under either the old RO structure or the new CfD Structure.[139]
123. DECC has belatedly acknowledged that access
to the market is a serious problem and on 5 July 2012, it launched
a call for evidence "to help independent renewable generators
access the electricity market".[140]
This is yet another example of the policy and practical arrangements
underpinning EMR still being in the process of formation.
124. Access to market for independent
generators under the CfD arrangements is an extremely serious
issue that must be resolved before a Bill can be introduced. We
recommend that DECC expedites its review of evidence on access
to the electricity market for renewable generators to ensure that
a solution to this issue is identified before the Bill is introduced
to Parliament in the "autumn".
125. One possible answer is to improve the liquidity
in the market. Ofgem has work underway in this area and is currently
consulting on proposals to require vertically integrated companies
to sell 25% of their generation output in the forward market.[141]
However, we heard concerns that Ofgem's current work would not
deliver sufficient liquidity and that it would probably not include
enough mandatory measures.[142]
Ofgem's evidence did not address the wider market liquidity issues.[143]
126. Three other potential solutions were put
forward:
- A "buyer of last resort"
mechanism could be introduced.[144]
The impact of this would be equivalent to a fixed FiT and capacity
using this route would not be responding to market signals (because
generators would be guaranteed a buyer, even when the market price
was low and indicating that their generation was outweighing consumer
demand). It would therefore go against the overall principle of
maintaining a competitive market.[145]
- Introduce an obligation (or some other incentive)
on suppliers to source energy from low carbon generation. For
example, by making a proportion of the costs of CfDs proportional
to the amount of low carbon energy they secure.[146]
- Delay the closure of the RO to new entrants.[147]
127. In paragraph 70 we recommended that the
FiT for small-scale generation should be increased to include
projects at least 10MW in size. This would eliminate the route
to market problem for all projects in this category. In paragraph
211 we make recommendations about the timetable for closing the
RO.
128. We recommend that as part
of its review of access to market for independent generators,
DECC should examine the following options: introducing a buyer
of last resort; introducing an incentive for suppliers to source
energy from low-carbon generation; extending the micro-gen FiT
to projects up to 50MW in size; and holding open the RO for new
entrants in the event that the PPA market disappears.
Other issues
LENGTH OF CONTRACTS
129. Clause 4 of the draft Bill allows the terms
of a CfD to include its duration. DECC's draft operational framework
for CfDs proposes that this will be 15 years for renewable technologies
and 10 years (with the possibility of varying this) for CCS projects
under the commercialisation programme. The Government has not
yet formed a view on how long nuclear CfDs will last for, but
says it would expect no less than 15 years.[148]
Renewables and CCS organisations argue that the length of CfDs
for their technologies should be linked to project lifetime and
therefore longer than the 15 or 10 years proposed.[149]
SETTING THE STRIKE PRICE
130. Clause 5 of the draft Bill allows for the
setting of strike prices either administratively, competitively
or through a combination of the two methods. Initially, strike
prices will be set administratively for each technology, before
moving to the use of auctions. The negotiation processes will
be different for different types of low-carbon energy:
- Renewables:
the process will be similar to the most recent RO Banding Review.
The System Operator (National Grid) will conduct an analysis of
costs and deployment potentials, which will feed in to a cost
benefit analysis of different strike prices on security, carbon
and cost objectives. Based on this analysis, a report from a panel
of experts, andpossiblythe advice of the Committee
on Climate Change, the Secretary of State will make a decision
on the strike prices. However the experience of the latest RO
review, when for example the decision about the support for onshore
wind was widely rumoured to be the subject of disagreement between
DECC and the Treasury, does not inspire confidence among potential
investors that the process will be determined exclusively by an
objective analysis of the available evidence.
- CCS: for early stage
CCS projects (including those supported under the CCS Commercialisation
Programme), there will be a negotiation between developers and
DECC. It will be possible to set different strike prices for different
projects in order to take account of the wide variety of technologies
and location-specific costs.
- Nuclear: the level
of the strike price will be determined through an administrative
price setting process, which will involve "negotiation with
developers on a project by project basis". [150]
THE STRIKE PRICE FOR NUCLEAR
131. Witnesses raised concerns about transparency
in setting the nuclear strike price in bilateral negotiation,
with little opportunity to move to auctions or competitive price
setting. [151]
Although Vincent de Rivaz (EDF) told us that "the strike
price will not be defined in a cosy way through hidden decisions"
and that the result would be "absolutely open and transparent",[152]
Richard Hall (Consumer Focus) was not convinced:
In a bilateral negotiation where there is only one
player in the room and that player can say, "Take it or leave
it; these are our terms", I have very little confidence that
that is an efficient way of deriving a price.[153]
132. Which? recommended that further detail was
needed in the Bill about how contract negotiations will be made
transparent, how arrangements will be scrutinised and how the
Government and System Operator will be held accountable.[154]
133. The Government is proposing that an "expert
panel" will be appointed to scrutinise the System Operator's
assessment of costs and deployment potentials for renewables.
We asked the Secretary of State whether an expert panel might
also scrutinise the negotiation of the nuclear strike price. He
told us: "We do not currently believe they should have a
role".[155]
134. We are concerned that the
proposed process for setting the nuclear strike price lacks sufficient
transparency. The perception that decisions are being made "behind
closed doors" could be highly damaging to the low-carbon
agenda and may further undermine consumer trust in energy companies.
It is essential that the negotiations deliver, and are perceived
to deliver, value for money to consumers. We recommend that an
independent panel of experts should be appointed to oversee the
negotiations and to report to Parliament on the adequacy of the
outcome and value for money for consumers.
THE LIKELY COST OF NUCLEAR
135. Witnesses from environmental NGOs, argued
that the strike price for nuclear was likely to be higher than
that for renewables, perhaps as much as £160/MWh.[156]
We note that a Times report of the 16th July 2012 indicated
that the asking strike price for new nuclear would be £165/MWh.
Vincent de Rivaz (EDF) however said "we are confident that
the strike price agreed will reveal the competitiveness of nuclear
new build compared to other forms of low carbon generation".[157]
136. Since there is little
competitive pressure or prospect of moving to auctions for new
nuclear, we are concerned that the strike price for nuclear could
be driven upwards. We hope that industry claims that the cost
of nuclear is competitive with other forms of low-carbon energy
will be reflected in the offers they put forward during strike
price negotiations. We do not believe that a nuclear strike price
higher than that given to offshore wind would represent good value
for money to the consumer. The Secretary of State should not agree
to contracts of this nature.
LONGER-TERM PRICE VISIBILITY
137. To provide developers and investors with
the visibility to make investment decisions, the draft operational
framework for CfDs proposes that five years of strike prices for
renewables will be published in the delivery plan in late 2013
with indicative prices in the draft delivery plan, published in
mid 2013.[158]
138. Aquamarine Power (a company involved in
developing wave power devices) told us that they needed more certainty
about what the strike price would be on a longer timescale. It
said:
It is the strike price for marine energy after
2017 which is critical for the growth of the marine energy
industry. We remain concerned that early-stage investors will
find it hard to make an investment case for early arrays without
clear sight of the market towards 2020 and beyond.[159]
139. Government should provide
clarity on the strike price level beyond 2017 as soon as possible
in order to provide certainty and help secure investment for emerging
technologies, such as wave and tidal power.
STATE AID AND A "ONE-SIZE FITS
ALL" PACKAGE
140. EU state aid rules seek to ensure that Member
States do not unjustifiably distort the single market through
financial or other interventions. Any new scheme under EMR will
have to be submitted to the European Commission and many aspects
of the EMR proposals will need clearance.[160]
If a scheme or technology falls under previous case law or block
exemptions however, then the clearance process may be completed
quickly. Article 23 of the General Block Exemption Regulation
provides (subject to conditions, such as the amount of aid provided)
that environmental investment aid for the promotion of energy
from renewable energy sources is compatible with the single market.
[161]
141. SSE considered that the clearance process
for CfDs might be lengthened through them covering both renewables
and nuclear, to which Article 23 does not apply. [162]
There are also questions about the nature of the counterparty
and whether this could fall foul of state aid rules; if the Secretary
of State or a government owned body were the counterparty, the
funds could be perceived as belonging, albeit temporarily, to
the state and being directed by it. This might increase the likelihood
of a scheme being viewed as state aid.
142. DECC accepts that "the eventual assessment
[of whether CfDs amount to state aid] may depend on the detail
of policy design". If EMR is classified as state aid, DECC
considers that this should still be approvable under the Treaty
because:[163]
The EMR is designed to secure new investment in low
carbon generation, while maintaining energy security and diversity.
EMR will minimise costs to the consumer, and the specific instruments
under EMR are designed to minimise distortions of competition.
So long as the balance of assessment is positive, any aid should
be compatible with the Treaty.
143. The Secretary of State told us that "We
think we will find favour" with the EU, because the EMR proposals
share EU objectives. [164]
Nuclear wrapped up within an EMR package may therefore
pass an approval process, whereas if presented outside the package,
it likely would not. It is possible that the Commission will take
a view on different technologies, but DECC told us that they did
"not see the fact that we are notifying for nuclear necessarily
holding up any decision on renewables".[165]
144. Witnesses shared the widespread perception
that EMR, and specifically CfDs, are a fig leaf over support for
new nuclear.[166]
The Green Alliance thought that the state aid issue was probably
why the "obvious" and "simple" decision, to
have the government as counterparty, had not been taken.[167]
The REA believed that the state aid question had been driven by
nuclear, and it was a "great pity" that renewables had
been tied up in that policy.[168]
145. We conclude that state
aid as well as political considerations have influenced the design
of the CfD package, and have caused policy and financial support
for nuclear to be rolled up with that for renewables. Logic suggests
that the Government should differentiate nuclear from other low-carbon
technologies within an overall FiT regime. The Committee will
consider further the building of new nuclear and its associated
challenges later in the year.[169]
146. Given that the Government
(and the Committee on Climate Change) see nuclear playing a key
role in the future energy mix, Government should consider how
carbon and security objectives could be delivered if no new nuclear
is forthcoming.
65 DECC, Planning our electric future: a White Paper
for secure, affordable and low-carbon electricity, CM 8099, July
2011p 37; DECC, Electricity market reform: policy overview, Annex
B: Feed-in tariff with contracts for difference: draft operational
framework, May 2012 Back
66
Ev 137, Ev w34, Ev w130, Ev w165, Q 96 [Professor Mitchell], Q
237 [Mr Steedman] Back
67
Ev w165 Back
68
Q 49 [Mr De Rivaz] Back
69
Ev w29, Ev 161, Ev w61, Ev 168, Ev w62, Ev w66, Ev w71, Ev w74,
Ev 176, Ev 206, Ev w170, Ev w173, Ev 227, Q 7 [Ms Vaughan], Q
57 [Mr de Rivaz], Q 98 [Dr Kennedy] Back
70
Q 407 [Secretary of State], Q 24 [Mr de Rivaz] Back
71
Ev 232, Ev w79, Ev 178, Ev 211 Back
72
Q 433 Back
73
DECC, Impact Assessment, Electricity Market Reform - options for
ensuring electricity security of supply and promoting investment
in low-carbon generation, 12 July 2011 Back
74
DECC, Impact Assessment, Electricity Market Reform - options for
ensuring electricity security of supply and promoting investment
in low-carbon generation, 14 December 2010 , p 66, para 69 Back
75
DECC, Impact Assessment, Electricity Market Reform - options for
ensuring electricity security of supply and promoting investment
in low-carbon generation, 12 July 2011, para 100 Back
76
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012 p 68 Back
77
Q 424 Back
78
For example: Ev 117, Ev 123, Ev 130, Ev 137, Ev 151, Ev w37, Ev
w71, Ev w74, Ev w98, Ev 187, Ev w112, Ev 198, Ev 198, Ev 217,
Ev 221, Ev 227, Q 24, Q 25, Q 66, Q 156 [Mr Temperton], Q 193,
Q 239 Back
79
Q 66 [Mr McElroy] Back
80
Q 161 Back
81
Q 419, Q 424 Back
82
Ev 111, Ev 115 Back
83
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012 p 68 Back
84
Ev 130, Ev w61, Q 59 [Mr de Rivaz], Q 153 [Mr Kingsbury] Back
85
Ev 117, Ev 130, Ev 161, Ev 168, Ev w74, Ev w98, Ev 178, Ev w112,
Ev 198, Ev 198, Ev 206, Ev 211, Ev 227 Back
86
Ev 130,Qs 58-59 [Mr Sambhi, Mr McElroy, Mr de Rivaz], Q 69 [Mr
Sambhi] Back
87
Ev 137, Ev 151, Ev 198, Ev 206, Ev 211 Back
88
Ev 206 Back
89
Ev 116 Back
90
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012 p 80, para 36-37
Contracts which involve uncertain outcomes
might be classed as derivatives. Back
91
Ev 130; DECC, Electricity market reform: policy overview, Annex
B, Feed-in tariff with contracts for difference: draft operational
framework, May 2012 p 80 Back
92
Q 24 [Mr Marchant and Mr Anderson] Back
93
Ev 168 and Q 24 [Ms Vaughan] Back
94
Q 202 [Mr Gill] Back
95
Q 190 [Mr Rehmanwala] Back
96
Q 227 [Mr Rehmanwala, Mr Gill and Mr Smith] Back
97
Ev w115 Back
98
Ev 151 Back
99
Ev 130, Qs 58-59 [Mr Sambhi, Mr McElroy, Mr de Rivaz], Q 69 [Mr
Sambhi] Back
100
Q 59 [Mr Sambhi, Mr de Rivza] Back
101
DECC, Electricity Market Reform (EMR): Alternative Payment Model
for Contracts for Difference, (undated) Back
102
ibid Back
103
Q 263 Back
104
Q 269 [Mr Ripley] Back
105
Q 427 Back
106
Ev w101 Back
107
Q 431 Back
108
Ev 116 Back
109
Ev 211 Back
110
DECC, Control Framework for DECC levy-funded spending: questions
and Answers, 8 December 2011 Back
111
HM Treasury, Control Framework for DECC Levy-Funded Spending,
March 2011 Back
112
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012pp 25-26, para 28. Back
113
Ev w179, para 33 Back
114
Ev 130, Ev w37, Ev w74, Ev w89, Ev 227, Q 29 [Mr Anderson], Q
80 [Mr Sambhi and Mr McElroy], Q 161 [Dr Edge], Q 203 [Prof Newbery] Back
115
Ev 211 Back
116
Q 29 Back
117
Q 262 Back
118
Ev w89, Ev w98, Ev 198, Ev 211 Back
119
Q 160 Back
120
Q 20 [Ms Vaughan], Q 80 [Mr McElroy] Back
121
Ev 232, Ev 198, Ev 167, Ev w74, Ev w89, Q 17 [Mr Anderson], Q
109 [Dr Kennedy], Q 163 [Ms Hartnell], Q 194 [Mr Taylor] Back
122
Ev 116 Back
123
Q 109 Back
124
Committee on Climate Change, Meeting Carbon Budgets - 2012 Progress
Report to Parliament, June 2012 Back
125
Draft Energy Bill, CM 8362, May 2012, Introduction, p 28, para
56 Back
126
Ev w89, Ev w115, Ev 211 Back
127
Ev 130, Ev w58, Ev w86, Ev w130, Ev 221, Q 120 [Mr Skillings] Back
128
Ev 130 Back
129
German experience with degression, both planned and in response
to price reductions is discussed in:
DBCCA (2011) The German Feed-in Tariff
for PV: Managing Volume Success with Price Response, Deutsche
Bank Climate Change Advisors [Online] Deutsche Bank Group, Frankfurt,
Germany. May 23, 2011 and DBCCA. (2009) Paying for Renewable Energy:
TLC at the right price. Deutsche Bank Climate Change Advisors
[Online] Deutsche Bank Group, Frankfurt, Germany.
Investor preferences for stable regimes,
which avoid the perception that policies are over-rewarding unproductive
technologies is discussed here.
Gross, R., Heptonstall, P. & Blyth,
W. (2007) Investment in electricity generation the role of costs,
incentives and risks, UK Energy Research Centre, London, UK Back
130
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012 pp 82-83 Back
131
Q 213 [Mr MacDougall] Back
132
Q 190 [Mr MacDougall] Back
133
Q 181 Back
134
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012p 83, para 7 Back
135
Ev w161 Back
136
Q 279 [Dr Edge] Back
137
Ev 198 Back
138
Ev 117 Back
139
Ev 117 Back
140
DECC, A call for evidence on barriers to securing long-term contracts
for independent renewable generation investment, 5 July 2012 Back
141
"Ofgem sets out road map to open up electricity market for
independent suppliers", Ofgem press release, 22 February
2012 Back
142
Q 211 [Mr Smith and Mr Taylor], Q 212 [Mr MacDougall] Back
143
Ev w115 Back
144
Ev 117, Ev 130, Ev 172, Ev 198, Q 187 [Dr Edge] Q 210 [Mr MacDougall
and Mr Gill] Back
145
Ev 198 Back
146
Ev 117, Ev 198 Back
147
Ev 198 Back
148
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012, pp 55-57 Back
149
Ev 130,Ev w31, Ev w52, Ev 198, Ev w161 Back
150
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012 pp 11-17 Back
151
Q 189 Back
152
Q 144 Back
153
Q 248 Back
154
Ev w54 Back
155
Q 543 Back
156
Ev 137, Ev w37, Ev w130 Back
157
Letter from Mr de Rivaz to Tim Yeo MP, 5 July 2012, available
at: www.parliament.uk/eccpublications; Ev 165 Back
158
DECC, Electricity market reform: policy overview, Annex B, Feed-in
tariff with contracts for difference: draft operational framework,
May 2012 p 12 Back
159
Ev w58 Back
160
Q 488 [Mr Virley], Q 493 Back
161
Commission Regulation EC 800/2008; renewables defined as "renewable
non-fossil energy sources: wind, solar, geothermal, wave, tidal,
hydropower installations, biomass, landfill gas, sewage treatment
plant gas and biogases", i.e. not including nuclear. Back
162
Ev 232 Back
163
Ev 109 Back
164
Q 486 Back
165
Q 494 [Secretary of State] Back
166
Ev 137, Ev w37, Ev 172, Ev w148, Ev 221, Q 104 [Prof Mitchell]
Back
167
Qq 245-246 [Mr Benton] Back
168
Q 158 [Ms Hartnell] Back
169
Building new nuclear: the challenges ahead, 27 April 2012 Back
|