The transcript is an approved formal record of these proceedings. It will be printed in due course.

Oral Evidence

Taken before the Public Accounts Committee

on Monday 24 October 2011

Members present:

Margaret Hodge (Chair)

Mr Richard Bacon

Jackie Doyle-Price

Mrs Anne McGuire

Austin Mitchell

Nick Smith

Ian Swales

Amyas Morse, Comptroller and Auditor General, Ross Campbell, Value for Money Director, National Audit Office, Robert Prideaux, Director of Parliamentary Relations, National Audit Office, and Marius Gallaher, Alternative Treasury Officer of Accounts, HM Treasury, were in attendance.

Examination of Witnesses

Witnesses: Ursula Brennan, Permanent Under-Secretary, Ministry of Defence, Lieutenant-General Gary Coward CB OBE, Chief of Materiel (Land), and Vice-Admiral Paul Lambert, Deputy Chief of Defence Staff (Capability), gave evidence.

Q1 Chair: Welcome. A number of my Members want to try and keep this as a tight session. I am conscious that we let you down last time. It would be really helpful and the session will go much better-I know I say this to you, Ursula Brennan, every time-if you come at us direct, even if we do not like what you say. If you do that, we can probably get through many of the issues more quickly. As a starter, why is Bill Moore not here?

Ursula Brennan: There was some discussion with the Committee about this. With me are Bill Moore’s boss, Vice-Admiral Lambert, and Lieutenant-General Coward, who is, if you like, the delivery side. So this is the requirements capability side and the delivery side. Bill Moore was going to be here, but there was some discussion about Paul Lambert coming, then the Committee came back to us at the end of last week, by which time Bill Moore, thinking he was not required, had gone off-

Q2 Chair: Was this when I said, "Not four; we’ve got to have three in," and he dropped out?

Ursula Brennan: Yes. I am not sure what happened, but he thought he was not needed and he is on holiday today.

Q3 Chair: We may come back to that, because he was clearly the SRO.

Ursula Brennan: He is not actually the SRO.

Q4 Chair: That is what our papers tell us.

Vice-Admiral Lambert: The SRO for the ground close combat is Brigadier John Patterson. Bill Moore is responsible to me and the Joint Capability Board for looking at the whole of the land environment and making sure that there is coherence with all the programmes across the land environment. But specifically for land vehicles, I have a head of capability who works with the Joint Capability Board and he is a brigadier.

Q5 Chair: How long has he been in that particular post?

Vice-Admiral Lambert: He has only been in that post since September. Before that I had Brigadier Riddell-Webster looking after that post and he was in the post for nearly three years.

Q6 Chair: Generally it is much more helpful for us and in the style of the Committee and the nature of our recommendations to get the responsible officer in front of us. You are running a massive multi-million pound procurement programme. Can I ask you first, Ursula Brennan, at what level of expenditure do you take the decisions?

Ursula Brennan: I do not personally take the decisions in quite that way. The decisions are taken and approvals are done by the Investment Approvals Committee on behalf of the Department. There is a structure of delegations within that and the biggest programmes tend to get discussed at the Defence Board and the previous Secretary of State set up a Major Projects Review Board to look at the biggest projects and review them more generally. But approvals are done through the Investment Approvals Committee.

Q7 Chair: Who chairs that?

Vice-Admiral Lambert: The finance director, Jon Thompson, chairs the Investment Approvals Committee.

Q8 Chair: So the decisions on these armoured vehicles are taken there?

Vice-Admiral Lambert: At the IAC, yes.

Q9 Chair: Right. Then let me ask you the second question. I don’t know who wants to answer this one. What criteria do you use when you decide to cut armoured vehicle capability?

Ursula Brennan: The criteria that we used in the SDSR and then again in the thing we called the three-month exercise, which was announced in July, are a combination of actions needed to bring our budget into balance, the capabilities that we require as an organisation, and the capabilities that will most deliver the adaptable force that we set out in the SDSR. So Vice-Admiral Lambert is responsible for advising the Defence Board on, if that is our SDSR objective, what are the capabilities we need to deliver it and how should we prioritise below that.

Q10 Chair: Okay. So maybe you should answer the question. As far as I can tell from a rather complex Report, this was a £14 billion [1] budget in 2005, thereabouts, when FRES was invented. It is now about £5 billion. Why did you decide to cut from £14 billion to £5 billion? I accept that it was not each time, but why? We have wasted a lot of money as per usual in this area, but why on earth did you decide to cut such a lot out of this capability?

Vice-Admiral Lambert: May I just go back to the previous question before I answer that one, if you don’t mind, Chair? Investment Approval Committees make decisions on procurement and on spending. They do not make the decisions on which programmes are cut. I put up the arguments on which programmes we move ahead with and which ones we cut, basically on priorities and on capabilities.

Q11 Chair: Basically on what? What I am suspicious of is that you do it because you don’t have the contract.

Vice-Admiral Lambert: There is always a degree of pragmatism within it.

Q12 Chair: How much is the pragmatism and how much is the capability?

Vice-Admiral Lambert: It is a combination of both. If one does not have enough money for the programmes one has for the next few years, there is no point in cancelling a programme where the liabilities will be greater than the savings.

Q13 Chair: Let me put it to you that I think on this programme, because your contracts are not there, you have cut it. It is a massive cut from £14 billion to £5 billion odd. That is a heck of a cut. You are a third of what you originally intended it to be. In today’s prices £14 billion would probably be £25 billion, knowing the MOD. So that is a massive, massive cut. The driving force was that you were not contractually committed.

Vice-Admiral Lambert: I would not disagree with you, Chair, but there is an awful lot that went into the programme in the past that was wishes. People thought that if they put a requirement in the programme, it would be delivered, whereas the totality of the equipment programme was not affordable. We needed to get down to an affordable programme before we started.

Q14 Chair: You could say that across the piece. I remember-this was on the previous Government’s watch-when Sarah Bryant was killed in 2010 [2] . The press coverage in The Guardian at the time reported that, "soldier after soldier came forward to express the concerns they had felt when they heard they would be using lightly armoured Snatch Land Rovers for their mission in Helmand province." What we ended up with, according to some sources, was 35 deaths caused by roadside bombs in Afghanistan, because we did not have the right armoured vehicles.

Vice-Admiral Lambert: I would dispute that. I think that the procurement of the right vehicles for Afghanistan, through the urgent operational requirements process, delivered the capabilities that we required in that theatre.

Q15 Chair: So all these press reports are wrong, are they? I remember this period rather well, because that was evidence that came out at the time. It was just when the previous Prime Minister was giving evidence to the Chilcot inquiry. He was faced with the accusation that he had not put enough money into the system. The two are connected. At that time in 2010, people died because they did not have the right vehicles, because we cut, because we were not contractually committed.

Vice-Admiral Lambert: In 2010, I can assure you that the urgent operational requirements process had delivered the right vehicles to the right theatres. At that time, we would have had Mastiffs for PPVs. We would have had the whole gambut of protected vehicles, which we had spent a couple of billion pounds on, through the requirements from the Treasury. I would dispute what you said for 2010.

Q16 Chair: Too often we are forced to use evidence that is given to us by other people. The minutes of a meeting held in 2011 of 16 Air Assault Brigade commanders, which was quoted in your Report, state, "Mastiff and Ridgback never got above 65 per cent availability. Risk was taken when vehicles were not fully functional." A brigade source said that, "Ridgbacks and Mastiffs are supposedly mine-proof, so 65 per cent of capability is a disgrace. Afghanistan is dangerous enough without being let down by equipment."

Lieutenant-General Coward: Perhaps I can chip in as a soldier. I think that it is fair enough to say that 65% is not enough availability. The requirement is 80% of the available fleet. It is only very recently-about a month ago-that we have consistently achieved 80% availability with the vehicles that you speak of: the Mastiff and the Ridgback. It is fair to say that 65% was not good enough. When you urgently deploy these vehicles into theatres, it takes time to build up the spares and the resilience, so that you can learn and maintain them on the road as well as you would expect. I would add that part of the reason why only 65% were available was down to the fact that many of them had been struck by IEDs in 2009 and 2010. We were struggling to repair those quickly enough and get them back on the road. No, it was not good enough, but it has got much, much better. I suspect that if you spoke to Ed Davis, the returning commander of 3 Commando Brigade, he would tell you that he was more than satisfied with the availability that is now being delivered.

Q17 Chair: I am glad to hear that, but I have to say-this is not a criticism of you-that what has clearly happened, in this terrible saga that we are looking at today, is that you had huge cuts to a key programme, which meant that you were left vulnerable without the appropriate vehicles that would have not been impacted by IEDs, or that might have been more resistant to IEDs, or that could have gone over territory in a way that your vehicles did not, so that they did not hit IEDs. There were all sorts of capabilities that you required in theatre that simply weren’t there, because in the MOD’s traditional way they were cut-an easy-cut programme, where there is no contractual commitment-thinking not about the defence need but about the financial imperative. Do you want to comment on that? You looked as if you were agreeing with me, Lieutenant-General.

Lieutenant-General Coward: I do agree, because we had to deliver urgent operational requirements. But even the Americans, who have dollars to spare so to speak, went out and bought new vehicles because even their Stryker vehicle, which was perhaps one of the vehicles that we were looking to procure for our core programme, was overmatched by the threat. A properly resourced core programme will allow you to deploy into harm’s way in a reasonable level of risk, but there will still be risk, and we found in both Iraq and Afghanistan that even a well-equipped AFV fleet is challenged by heavy IEDs and externally forged fragments.

Q18 Chair: Okay, but on that-then I’m going to go to Nick and then Ian-let me just quote to you from Peter Flach, who you probably know well from RUSI. I am interested in benchmarking our performance against other countries and what he says, talking about armoured vehicles, is this: "The failure of the UK to derive affordable requirements is recognised in the AFV"-that’s armoured fighting vehicles, I assume-"industry. The industry likes customers who know what they want and can afford it, such as"-this is the really scary bit-"US, Canada, Australia, Germany, the Netherlands and Belgium. They have other customers who either do not know what they want or haven’t got the money for it, and these are more of a problem. Too often the UK falls into a third category of being unable to decide what it wants and not having the funds."

I have to say that that is an outrageous condemnation of our whole procurement process in this one absolutely key area, benchmarked against everyone else. What is your view of that, Lieutenant-General?

Lieutenant-General Coward: Peter is entitled to his opinion. I would not put us third; I would perhaps put us in the second rank. We have been indecisive. We have had well-recorded difficulties with the FRES programme, as this Report reflects, and that is a fair criticism. But we have learned lessons from that period of indecisiveness and over-aspiration, and I believe that our programme is beginning to head in the right direction.

Chair: I’m just going to ask Paul Lambert and then Ursula Brennan to comment on that, and then I’ll come to you Nick.

Vice-Admiral Lambert: If one looks back a few years, as we moved out of the cold war the UK was of a mindset that we wanted deployability for our armed forces. That was a key criterion, which drove us down the route of looking at lightweight armour and equipment that you could deploy very quickly on aircraft, and I think that we learnt a hard lesson in places such as Afghanistan and Iraq that protection is more important than deployability. That is one of the reasons why we went down the urgent operational requirements route, and many of the vehicles now are a lot heavier than we had envisaged five or 10 years ago.

Q19 Chair: Are we worse than America, Canada, Australia, Germany, the Netherlands and Belgium at making these decisions, which is what he asserts?

Vice-Admiral Lambert: I agree with the General that we have changed our mind over the past few years, but part of changing our mind is because we have learned some hard lessons on deployed operations, and we have conducted a lot of deployed operations over the years.

Chair: I will take that as a yes.

Ursula Brennan: I think we do acknowledge that we had over-complex requirements and an over-complex procurement route for some of our attempts to purchase armoured fighting vehicles in the past. The only thing I would say is that in relation to theatres-Iraq and Afghanistan-it is genuinely the view in the Ministry of Defence that even if we had made up our minds and stuck with the procurements that we were intending to do, and even if they had come in speedily, we would still have needed to procure urgent operational requirements for Afghanistan.

It would be a pity if the Committee were left with the impression that people had died in Afghanistan because of our shilly-shallying about the procurement of armoured fighting vehicles, because the thing that mattered for Afghanistan was our recognising speedily what the requirements were and delivering them. Our core programme gave us some base vehicles, but the thing that we needed to do to respond to those threats was to be really speedy in getting the UORs into theatre. That is what we put all our energy into doing.

Q20 Chair: I have to say that it is your own commanders on the ground who say that. It is the people with whom Lieutenant-General Gary Coward works. It is not this Committee. It cannot make sense to dump a billion quid of a planned programme and then spend £2.8 billion of actual Treasury money, which is probably the reason that you did it, on second-rate alternatives. That cannot make sense in any world to dump a billion there and spend £2.8 billion over there.

Vice-Admiral Lambert: I would not say that the protective vehicles that we have for Afghanistan are second rate at all.

Q21 Chair: You are going to have to spend a lot of money on them, aren’t you?

Vice-Admiral Lambert: Yes, but we have given our soldiers in Afghanistan the level of protection that no other country has got in their protective vehicles.

Q22 Chair: You dumped a billion and you spent £2.8 billion. Anyone with a little bit of common sense knows that there is something awry in that. You must see that yourself.

Vice-Admiral Lambert: The dumping of nearly a billion for going down the wrong route and for a whole variety of-

Q23 Chair: It was not the wrong route. It was a route you decided you could get out of when you had more commitments than you had money. It wasn’t the wrong route in terms of defence capability. It was a route that you got out of as a short-term decision and you then got an extra dollop of money from the Treasury.

Q24 Comptroller and Auditor General: Can I make sure that we have this point clear? If I understood Vice-Admiral Lambert correctly, if we had gone ahead more quickly with procuring conventional vehicles at that time, the likelihood is that they wouldn’t have been proofed against the blast devices that were deployed in Afghanistan and they probably would have ended up having to buy more vehicles anyway. Just for clarity, our Report is not suggesting that there is a direct crossover between the vehicles you might have needed in Afghanistan-you might have been able to use them-and the others.

Q25 Nick Smith: Your last question touched on the point that I was trying to understand, which is the business of overall performance. We were a bit disconcerted by Vice-Admiral Lambert’s point about things in the round having gone "rather well". I would still appreciate the Department acknowledging point 6 in the Report, which is that the Department has managed to spend over £1.1 billion through the standard acquisition process since 1998 without delivering any of its principal armoured vehicle projects. Are you going to acknowledge that point?

Ursula Brennan: Sorry, could you quote the reference again?

Nick Smith: It is on the first page-excuse me, it is from our briefing.

Mr Bacon: It is on page 6, paragraph 4: "The list of armoured vehicles projects cancelled, suspended or delayed in Figure 1 suggests that…the Department’s standard acquisition process for armoured vehicles has not been working."

Ursula Brennan: We have acknowledged that there were failings in our procurement of armoured fighting vehicles. Yes, we do acknowledge this.

Q26 Mr Bacon: Who has paid the price for that? Who has paid the penalty for that scale of error? Because for most of this decade-although we have had an enormous financial crunch since 2008 or late 2007-it was a period of rising Government spending. It is a huge failure. Who is paying the penalty for that? Is anyone?

Ursula Brennan: The reasons-

Q27 Mr Bacon: Apart from the soldiers on the ground, obviously, who has paid the penalty for this failure in the Ministry of Defence?

Ursula Brennan: The reasons-

Q28 Mr Bacon: No, no, my question is who? The answer must be a person or no person.

Ursula Brennan: The reason why I wanted to say the reasons is because the reasons why certain programmes were stopped or cancelled were to do with decisions that were taken, in some cases about the procurement routes, between Ministers and officials at the time about the way it was chosen to procure-

Q29 Mr Bacon: You are answering a question that is not the question I asked. You are giving me an explanation of how we reached this position through decisions having been taken. Plainly, some decisions must have been taken for us to end up in a particular position. There must have been bad decisions for us to end up in a particularly bad position such as this one. My question is who has paid the penalty for this in the Ministry of Defence? It’s a simple question. Who?

Ursula Brennan: I can’t point the finger at one person, because there isn’t one person who was responsible for the different sets of decisions that were taken about individual vehicles.

Mr Bacon: Is there anybody who has paid the penalty for this?

Vice-Admiral Lambert: If I can-

Mr Bacon: No, no, no. I am looking at Ms Brennan. I am asking her a question. She is the accounting officer. She is the permanent secretary. My question stands; I’ve asked it three or four times now. It is very simple and very clear. Is there anybody in the Ministry of Defence who has paid a penalty for this?

Ursula Brennan: No. I don’t think I can point the finger at anybody.

Q30 Nick Smith: What tasks outlined in the SDSR will the armed forces not be able to carry out due to the lack of armoured vehicles, given that we are going to wait so long for the ones that are planned to come through?

Vice-Admiral Lambert: In the whole gamut of capabilities, we are able to do all the capabilities we require, but maybe not at 100% in the way we’d like to. I will give you an example. Within the armoured vehicles is a vehicle for reconnaissance. You will see that we have a programme for the future for reconnaissance, but our present reconnaissance vehicles are fairly aged. Does that mean we can’t do reconnaissance? No, because we can do reconnaissance using overhead assets. We can use helicopters and other vehicles. The specific vehicle has not been delivered in accordance with the programme, but it doesn’t mean that the capabilities aren’t there or being delivered in a slightly different way. We have to look at the balance of capabilities. The Report is specific about vehicles rather than the capabilities that those vehicles deliver.

Another example is how we move people around the battlespace. There is a programme in here for a utility vehicle, which is all about how we move soldiers around the battlespace, but it doesn’t mention helicopters, which is another way of moving people around the battlespace, or any other types of vehicle that we procured. Is there any capability that we can’t do? No. Are there capabilities we would like to do better and in a different way? Yes. If these programmes had delivered, there would be different ways of doing it. That is where we are trying to get to.

Q31 Nick Smith: It sounds like you are saying that we are not going to have the capability and that we are going to have to do it in a different way, which may not be as effective.

Vice-Admiral Lambert: I won’t disagree with you on that. I won’t disagree.

Q32 Chair: And what do you feel, Lieutenant-General?

Lieutenant-General Coward: That’s a fair answer.

Q33 Chair: What are you not going to be able to do?

Lieutenant-General Coward: I don’t think you can say specifically as yet. As I think you will appreciate, the funding available for the armoured vehicle programme has now been set, and the Army is reappraising what the best mix will be within that pipeline of funding. We would be crystal ball-gazing to say, "We couldn’t do reconnaissance in the way we would like. We couldn’t do armoured infantry, couldn’t do this or couldn’t do that." There will be compromises that we will have to make.

Q34 Chair: Have you got enough helicopters? My information is that there aren’t even enough helicopters.

Vice-Admiral Lambert: The announcement that we were moving ahead with the Chinook programme gives us the capability-

Q35 Chair: When?

Vice-Admiral Lambert: The order has been made, and they are in production at the moment.

Q36 Chair: Will you have enough helicopters?

Nick Smith: Particularly for reconnaissance, given you’ve highlighted that as problem.

Vice-Admiral Lambert: We have enough helicopters for Afghanistan at the moment. Have we got enough helicopters for Future Force 2020 and all the missions that we’re likely to want? With the timetable for delivering we will look at what capability shortfall-

Q37 Chair: What does that mean? When are you going to get them? Will there be enough?

Lieutenant-General Coward: The new Chinooks will start coming in in 2015.

Q38 Chair: In 2015. How many have you ordered?

Lieutenant-General Coward: Fourteen.

Q39 Chair: So you will get the first one in 2015 and the last one in-

Lieutenant-General Coward: I think slightly before that. But their capability, with people trained, will be around 2015 [3] .

Q40 Comptroller and Auditor General: As I understand it, the argument says, "Of course you can do reconnaissance with something other than one specific vehicle." Who could argue with that? You can use something else in your defence capability to do all those. Of course that makes sense. But when you’ve got less of everything, the amount of these tasks in total that you can do at one time steadily goes down, doesn’t it? Isn’t that also fair? It is an answer, but it is not a solution to everything.

Q41 Mr Bacon: Could you remind us what the Government’s policy is on British troops coming out of Afghanistan-the draw-down?

Lieutenant-General Coward: We are due to be out of combat operations by the end of 2014. The reduction over time between now and then is still being developed: will it be a glide slope, a cliff edge, a convex, or whatever?

Q42 Mr Bacon: The combat side is expected, at least under current plans, to be finished by the end of 2014.

Lieutenant-General Coward: Correct.

Mr Bacon: The helicopters arrive in 2015.

Lieutenant-General Coward: The additional helicopters, yes.

Q43 Mr Bacon: But they won’t be used in combat in Afghanistan if current plans are stuck to. Is that right?

Lieutenant-General Coward: Correct. The point is that they are, in part at least, replacing some platforms that will be going out of service in future. The Sea King, for example, of which we withdrew a number from Afghanistan last month, is going out of service in 2016. Replacing those as a capability for defence is, at least in part, what the additional 14 Chinooks will do.

Q44 Mr Bacon: Are the additional 14 Chinooks we are getting an advance on the Mk 3? What are they?

Lieutenant-General Coward: They will be described as Mk 6 and combine the latest European cockpit with an American upgrade to a digital platform. They will provide a full range of capability, not in exactly the same way as the Mk 3-

Mr Bacon: One hopes not.

Lieutenant-General Coward: The Mk 3s are now flying in the UK and providing valuable output for training crews and soldiers.

Q45 Mr Bacon: I hope so, given how much you’ve paid for them. Will you tell us how much the new Chinooks will cost each?

Lieutenant-General Coward: I cannot give you that answer; I don’t have it.

Vice-Admiral Lambert: We’ll have to come back to the Committee on that.

Q46 Chair: Can we get a logical issue out of this? The Chinooks are replacing something else; they are not replacing the armoured vehicles that you have cut out of your programme.

Vice-Admiral Lambert: I think the Comptroller and Auditor General put it quite well.

Q47 Chair: It could be done, but you haven’t got the capability. You haven’t got enough of them to do it.

Vice-Admiral Lambert: We will always try and mix our equipment so that we provide the capabilities. What happens is that it has to be stretched thinner across the total requirement.

Chair: Not very satisfactory.

Q48 Ian Swales: How many people work in the MOD areas that look after the purchase of armoured vehicles?

Lieutenant-General Coward: I don’t have the real number. I would hazard a guess that, in the MOD and the requirement-setting organisation, we are talking about handfuls.

Vice-Admiral Lambert: No more than a dozen.

Lieutenant-General Coward: In Abbey Wood my guesstimate-it is but that-is about 200 or 300 at the most [4] .

Q49 Ian Swales: That is far fewer than I expected. The Committee heard a much higher number just for helicopters, so I am quite surprised at that. Having said that, a heading on page 14 of the Report states, "A reluctance to compromise in setting armoured vehicle requirements puts delivery at risk", and on page 16 it states, "The armoured vehicles’ requirements setting process has proved insufficient in a rapidly changing operational environment." If you meet manufacturers of defence equipment-the Chair mentioned this earlier-there is a constant cry that we keep on changing our minds and we don’t know what we want. We keep changing requirements and asking them to change from standard designs and so on. Can you comment on the way that we buy this type of equipment?

Vice-Admiral Lambert: I do not disagree with what the Report says. I think it is right that in the past we have asked for everything rather than honed down and headed towards a more off-the-shelf solution. The TRACER programme, with which the Report starts, needed cutting-edge technology right across the piece from how the propulsion would work through to the type of armour and gun needed. That was too big an ask; it was always going to be expensive and was too high a risk.

Q50 Chair: Were you involved in that decision?

Vice-Admiral Lambert: No. The programme started in 1992, I am afraid, Chair.

Q51 Chair: And when did you come to this project-how long have you been in this post?

Vice-Admiral Lambert: I have been in this job just over two years. The TRACER programme started almost 20 years ago.

Q52 Ian Swales: And what has it delivered and at what cost?

Chair: It hasn’t delivered anything.

Vice-Admiral Lambert: It hasn’t delivered nothing.

Q53 Ian Swales: At what cost?

Chair: £700 million [5] .

Vice-Admiral Lambert: We have been moving towards more off-the-shelf procurements and a lower set of requirements to make things more affordable. That process has been moving that way across the piece.

Q54 Ian Swales: Are we in the middle of any of those similar programmes, where we will spend far more than we expected and achieve little or nothing as a result? Can you think of another such programme we will be hearing about in this Committee in the future, or have we learned the lessons from this programme and completely changed?

Vice-Admiral Lambert: I do not think we have completely changed; I think we are in the process of changing. I do not think we can yet draw a line underneath all the asking we have had in the past, but if you look across the whole of the three environments-maritime, air and land-we are moving towards a more sensible approach and a more off-the-shelf approach, and we are getting away from asking for the very top, high-end specs, which we never deliver anyway. We have to move to a solution set which we can upgrade often, and we need to be able to afford to do that, rather than to afford one or two very high specs.

Q55 Ian Swales: As the accounting officer, Ms Brennan, are you happy that that culture, which Vice-Admiral Lambert has described, is now embedded in the MOD?

Ursula Brennan: I was just going to comment that I think we have learned lessons, and some of that is beginning to be visible in the procurements that are ongoing at the moment, like Foxhound, maybe also Terrier, and some of the FRES arrangements. There are things that we learned about buying in batches; having a simpler contract structure with a prime contractor, and not trying to have the complex contract structure that we had before and making sure that industry is ready and able to deliver the capabilities that we are after, and that we are not asking for something that is at the leading edge.

There are three other key things that we have done. One is that we are absolutely clear about not committing to expenditure when we do not have the money in the budget line. We are clear about being able to say, even if there is a reduced budget, that we expect to be able to spend it, and we do not have to go back and dig it up, because it is in balance. That is one thing that we have learned.

The second thing relates to giving the Army clearer responsibility for making decisions in this area, and similarly the Navy, with ships, and so on. We then have a stronger sense of, "Here’s the budget and here are the objectives we’re trying to achieve. Now, you come up with a proposition and own it."

Thirdly, our new Chief of Defence Materiel, Bernard Gray, is engaged in a major programme of rethinking the way we actually do all this procurement down in Abbey Wood to change the kind of project teams and the way they think about how they do procurement.

Q56 Ian Swales: Specifically on armoured vehicles, we heard from Mr Smith about the delay in getting what the 2010 SDR said we needed, and we heard that it would be 15 years before we got it. What is the cause of that delay? Is it simply budget availability, or are we in the process of some major technological innovations, which are delaying all this? Are we just talking about the budget? We all have to be concerned whether the technology will still be okay in 15 years’ time and, given what the Report says about this programme perhaps being sacrificed sometimes to overspends elsewhere, whether we will even make the 15-year horizon.

Ursula Brennan: That was the point I was trying to get at. If we have our budget in balance, we do not have to go back and unpick programmes because there is not the money there. Just at the moment, we are looking at what happened in Libya, and asking what lessons we learned and what the implications are for equipment. That is inevitable and will lead to urgent operational requirement-type approaches. The thing we can try and stop is having to have volatility driven by problems in the budget.

Q57 Chair: Can I come in on this? This is the narrative that we have heard before, and the reality is very different. I am just going to put it to you that if your budget worked, you would not have had to do the three-month review. You have just pulled out money because you were going to spend more in 2011-12 than you had in your budget. That is right, isn’t it? That is what the three-month review is about.

Ursula Brennan: The three-month review was not about 2011-12. It was about the 10-year programme.

Q58 Chair: But you have cut 2011-12 spending on this programme.

Ursula Brennan: Not, I thin as part of the three-month exercise. I am not sure.

Q59 Chair: The sum of £2.8 billion sticks in my memory. Perhaps Ross Campbell-

Ross Campbell: That’s over 10 years, Chair.

Q60 Chair: And how much in this year?

Ursula Brennan: I am trying to recall. I don’t dispute that over different planning rounds we have been taking money out.

Q61 Chair: But this year?

Ross Campbell: It is just £3 million this year, Chair. The bulk of it is spread over the next 10 years.

Q62 Chair: Nevertheless, you have cut. The other thing is this: is your budget in balance?

Ursula Brennan: I think that the words that the previous Secretary of State used when he made the three-month exercise-

Q63 Chair: You tell me. You are the accounting officer.

Ursula Brennan: Were "broadly in balance". And that is my view.

Q64 Chair: You tell me. Is it in balance?

Ursula Brennan: It is broadly in balance. It is not yet completely in balance.

Q65 Chair: What does "broadly" mean? How much are you over-committed to what you have got?

Ursula Brennan: We are in the process of conducting the planning round, which will enable us to-

Q66 Chair: Don’t tell us that you are getting better at it, because you are doing another planning round to cut more. "Broadly in balance" means you are not in balance, so just tell me how much over you are at present?

Ursula Brennan: I can’t tell you the answer to that, because we don’t-

Q67 Chair: I bet you can-you are just not willing to share it with me.

Ursula Brennan: No, no. I genuinely cannot tell you the answer to that, because we are in the middle of a planning round.

Q68 Chair: But you can tell me what the planning round is trying to identify.

Ursula Brennan: The planning round is trying to make sure that the process that we started in the strategic defence and security review, and that we took a stage further and nearly completed in the three-month exercise, needs to be completed in the planning round that we are doing now. The National Audit Office will actually be auditing these numbers very shortly and you will have an opportunity to see-

Q69 Chair: The NAO will audit it after you have done it, but for you to sit and tell the Committee, "We’ve now learned all these lessons; we’re in balance", is not true, because you have had a three-month round and you are now having what you call a planning round, which to me is just an in-year budget cut because you have got too much. That must be right.

You are not willing to share with us by how much, but currently if you did not have this last bit of cuts you would be overspending in 2011-12. Am I right about that? Just tell me yes or no on that. Maybe that is the best way of putting it. If you did not have this final planning round-that is what you call the cuts exercise that you are currently engaged in-you would be overspending in 2011-12.

Ursula Brennan: The three-month exercise was predominantly not about 2011-12.

Q70 Chair: No, but you’re doing another planning round now.

Ursula Brennan: We’re doing a planning round, but not for 2011-12. 2011-12 is the current financial year. We are doing a planning round that is looking at forward expenditure, not at the current financial year.

Q71 Chair: And this year "broadly in balance" means "not in balance", but you are not prepared to share with us how much you are over.

Ursula Brennan: Just to be absolutely clear, we will deliver our budget in the current financial year. We have said, and it is correct, that we are broadly in balance over the decade. We are not yet completely in balance over the decade. That is what we are seeking to get to.

Q72 Chair: And how much are you out?

Ursula Brennan: Well, we are doing the planning round to reach that conclusion. We will deliver our budget in the current financial year. We are trying to get-it is very difficult to do this in one go. We made decisions in the SDSR; they have knock-on effects; in the three-month exercise, we made the change around reserves and regulars, and the Germany rebasing; and all of those things have to knock through. Our intention is to get to a balanced budget and to have it audited by the NAO.

Q73 Chair: So the SDSR is what we have all said-it was set without having regard to the financial implications of it. That is the problem you are now picking up.

Q74 Nick Smith: Does that mean that you will delay the implementation of the Warrior upgrade? What will happen to that?

Ursula Brennan: The previous Secretary of State announced that we would be proceeding with the Warrior upgrade when he made his statement in July.

Q75 Nick Smith: Will it happen on time or will it be delayed?

Ursula Brennan: When he made the announcement, I don’t know that he-

Q76 Nick Smith: So the plan is for them to arrive on time. And what will happen to Scout?

Ursula Brennan: There were certain things that the former Secretary of State announced on 18 July, and those things we are clear about. We are engaged in the piece of work that the Army is doing about the rest of the equipment programme, within that envelope of funding that we have given it. So I cannot give you any other details yet, because the Army is working that through.

Q77 Austin Mitchell: In retrospect, it looks as though there is a certain amount of budget juggling going on at the Ministry of Defence, which speaks to a certain amount of chaos. You have spent £2.8 billion from the Treasury’s reserve by the urgent operational requirements, but then you took out £1 billion from the standard vehicle budget to fund other areas of defence. This is juggling, isn’t it? What other areas of defence were being funded from the standard budget?

Ursula Brennan: I would not quite describe it as saying we took it out of armoured fighting vehicles to fund defence, because if you are alluding to the-

Q78 Austin Mitchell: Well, you are getting money from the Treasury and not using your own budget.

Ursula Brennan: These are two distinct things. The urgent operational requirements are about specific vehicles to meet the specific threat-

Q79 Austin Mitchell: Yes, improvisation.

Ursula Brennan: Not just IEDs, but other things to do with the weather, the heat-all sorts of things for which we had to adjust our vehicles and get new vehicles. That was specifically for the threats in theatre. We have been seeking to balance our budget and taking money out all over the place to bring it into balance. We didn’t specifically target armoured fighting vehicles.

We did a balance that said "There is no point in taking out cost from programmes that are already on contract, where the liability is greater than the saving we can make." So yes, it’s true we looked at, first, the places where the spend was uncommitted; but that wasn’t the only reason why we came to-

Q80 Austin Mitchell: But that means you are getting the vehicles at a higher price, because paragraph 15 says that the cost would have been lower had more armoured vehicle projects of the Department’s core programme been delivered as originally planned; so you are paying more for the process of improvisation that is going on.

Ursula Brennan: It’s certainly true, and I think we have acknowledged, that there were failings in the procurement of armoured fighting vehicles, and if we had actually delivered some of those vehicles that we planned to deliver on time, clearly some of the cost would not have been nugatory.

Vice-Admiral Lambert: Some of the £2.8 billion has been spent on upgrading vehicles that are part of the core programme; but it is right that, if the core programme had delivered a vehicle for the troops, that would have been used instead of some of the PPVs, so I think that comment here is partly correct.

Q81 Austin Mitchell: Well, improvisation had to go on, of course, because people were being killed, but let’s turn now the question of why the core programme didn’t deliver; because figure 1 on page 5-if you look at projects that are part of the core programme-looks as though you are making them over-elaborate or gold-plating them beyond the necessary technical limits. "Tactical Reconnaissance Armoured Combat Equipment Requirement…Cancelled". "Multi-Role armoured vehicle…Cancelled." "Future Rapid Effect System-Utility Vehicle…Suspended. "Future Rapid Effect System-Specialist Vehicle…Delayed: in-service." "Warrior Capability…Delayed: In-service". "Terrier armoured engineer vehicle…Delayed: in-service".

Why is all this going on? Why are you making such a cock-up of the standard budget? Or why did you? It wasn’t you; because as usual the people appearing before us have been appointed later than the mess; but why did the mess occur?

Vice-Admiral Lambert: I think the TRACER programme was started with the best intention, and there were several other programmes, which started with the best of intentions of trying to get to the cutting edge so that we could deliver equipment right at the forefront of technology-

Q82 Austin Mitchell: They were over-elaborate, though. Men were dying, meanwhile.

Vice-Admiral Lambert: No; the TRACER programme, which was cancelled in 2001, would have delivered a reconnaissance vehicle that would have been at the cutting edge anywhere around the world. It was over-elaborate. The multi-role armoured vehicle programme was something completely different. The requirement was for something that could be deployed very rapidly; with the MRAV programme, as it progressed the view was that it was going to become too heavy to be deployed quickly by air. In hindsight it probably wasn’t. In hindsight, the amount of armour that was going on MRAV was probably about right, and our priority of putting deployability over armour was not right. The UV programme got over-complex in the commercial arrangements and part of that was-and this is where they had systems of systems, integrators, etc-a commercial issue rather than an issue of requirement.

Q83 Chair: What did you get right?

Vice-Admiral Lambert: The Warrior programme was right. The whole of the UOR programme has created-

Q84 Chair: The Warrior programme was right but you have delayed it?

Vice-Admiral Lambert: Yes, it has been delayed.

Chair: Well, that’s not right.

Vice-Admiral Lambert: The Urgent Operational Requirements are right.

Chair: Tell me about that.

Vice-Admiral Lambert: Things like Mastiff and-

Q85 Chair: That’s because you get money out of the Treasury. What did you get right? You just look at this and think there’s nothing right here.

Vice-Admiral Lambert: The procurement of those operational requirements-it doesn’t matter whether it came from the core budget or the Treasury-and the delivery to theatre were absolutely right for those programmes.

Q86 Chair: But they might not have been the right vehicles.

Vice-Admiral Lambert: They are right for that specific theatre.

Chair: So it isn’t right, in that when your predecessors have sat around and thought, "What does the Army need?", they haven’t come down to what you ended up getting in Afghanistan. Lieutenant-General Gary Coward has told us about the implications of that decision. It is very difficult to find anything you got right.

Q87 Mrs McGuire: The Department has almost undertaken a handbrake turn. We have gone from gold-plating and Christmas tree-or even, as I said once, gold-plating the Christmas tree-in the procurement process, to something that is more linked to a budget. Vice-Admiral Lambert, how have you managed to change the culture within the MOD? You said earlier that we are now looking at off-the-shelf and a capacity that is more limited than you might otherwise have attempted. How have you managed that change to alert people to the fact that they need to be more price-sensitive, and that, instead of going to Waitrose, they might also find that Asda has the same thing-the military equivalent-only cheaper?

Vice-Admiral Lambert: I think that "gold-plating" has got into our vocabulary and we need to be careful about it. I don’t think anybody starts off with the idea that they want a gold-plated solution. They want a solution that, when we go into a conflict zone, protects the people and gives us a chance of winning. My predecessors have always ensured that we have the cutting-edge capability delivered to the theatres of war. What has changed is that, in the past, we used to deliver many of our platforms and we would use the same platform over a long time. So what was delivered on day one would be the same capability we were using 10 or 20 years later. One of the big changes in defence is the idea that you can upgrade quickly and cost-effectively. So the key platform needs to be upgradable and then we need to do a spiral development-a development over a period of time-so that you don’t need all the capability delivered on day one and can upgrade over a period of time. Then you can start looking at some of the key cost drivers of those programmes and driving them down. I think that has probably been one of the biggest changes of mindset-you don’t have to have everything on day one; you can get it over a period of time.

Q88 Chair: May I ask Lieutenant-General Gary Coward what cutting-edge capability in this area has been delivered to you over the past decade?

Lieutenant-General Coward: In the armoured vehicle area?

Chair: Yes. What cutting-edge capability have you had delivered?

Lieutenant-General Coward: Almost exclusively in the UOR field.

Chair: Cutting edge?

Lieutenant-General Coward: For the theatre? Yes, I would say so. It has been optimised for the theatre. On the basis that our protective mobility vehicles, on which we spend a considerable amount of money-

Q89 Chair: Optimised is not necessarily cutting edge.

Lieutenant-General Coward: I hesitate to say this, but since deploying those vehicles we have had casualties in them, but no one has been killed [6] . In our core vehicle programmes in Iraq, and in other vehicles, we have had casualties and many deaths, as you rightly reflected. So I do think that the Cougar family of vehicles and the Husky and so on are cutting edge. The Americans are procuring the same vehicles and we are putting cutting-edge armour on them, over and above that which the Americans produce.

Q90 Mrs McGuire: If you move from that position of cutting edge, what would be the impact on the safety of our personnel in theatre? You have clearly indicated that by going for the cutting-edge solution, you have delivered a far safer environment for our personnel, inasmuch as the theatre can be safer. Does it cause you nightmares that you are moving to this more off-the-shelf approach and that, in two or three years’ time, it may well be the case, although I hope not, that you will be back in front of another Commons Committee-not necessarily this one-trying to justify why you did not go for the cutting edge?

Lieutenant-General Coward: May I qualify what I was talking about? I specified UOR. In terms of our core programme, the vehicles that we are being, rightly, in my view, criticised about were aiming for the cutting edge-they were going for a close to 100% solution. We have learned by these examples that that is not a sensible thing to do, so in our requirement-setting we are now compromising, within the financial envelope available, to deliver the best balance of capability against cost. Yes, in future there will be those people who, when they attend a coroner’s court, might argue that if we had waited for a bit longer for another bit of technology, Rifleman X may have been saved, but if we wait that long we will not have any vehicle. So it is a balance between that requirement and what we can deliver in the time available.

Q91 Mrs McGuire: Do you think that Committees such as this conflate the two issues of the budgetary pressures and the procurement process, which has frankly left a lot to be desired? Should we actually be looking at the procurement process even within the new approach of having an 80%-or whatever-capability? Rather than concentrating on the budget, should we be looking at the procurement process?

Lieutenant-General Coward: You should look at both. There is a budgetary issue, which Mrs Brennan has addressed, and there is the requirement-setting and procurement process, which has been slow, lumbering and bureaucratic-it was aiming for the stars when, as it now is, it should have been much more pragmatic. With what we have done with the Warrior capability sustainment programme, with the Scout programme and especially now with the Foxhound, we are beginning to learn those lessons. You will have to judge us on that delivery.

Q92 Mrs McGuire: How do you benchmark whether you should go for the cutting edge, and there may well be circumstances in which you would want to go for the cutting edge, or for something that is closer to 80%-is it 80% or 75%?-of capacity?

Vice-Admiral Lambert: We look at upgradeability these days. One thing we are doing in our vehicle programmes is putting in the electronic architecture so that we can add things on afterwards. Getting that architecture absolutely right is therefore important and, after that, we can wait for what we will add on. It is really about looking at that upgradeability. Again, with vehicles and perhaps with other equipment, we are looking to make sure that we can upgrade them-that we have the space and the energy and propulsion plants that we can upgrade, rather than making sure that everything is there on day one.

Q93 Jackie Doyle-Price: I want to come back to figure 1. When you look at the figures, they show that, of the £1.1 billion spent, only £407 million has delivered any vehicles, so for £1.1 billion we have 160 vehicles. It’s not great, is it?

Ursula Brennan: I think we have acknowledged that there were failings. They were not all for the same reasons. Sometimes we entered into something with the Americans and the Americans pulled out, and we were left high and dry. Sometimes we were over-elaborate in our procurement route. There were a variety of different reasons. We acknowledge that it was not good that there were projects that we cancelled and had nothing to show for it. There are others, however, where money continues to be spent and the vehicles are actually in production. Terrier is in production, I think, so it will deliver.

Q94 Jackie Doyle-Price: So ultimately only £323 million has been completely wasted-okay.

I want to get to the bottom of why some projects might have been more successful. You just mentioned that other partners have pulled out of things. Looking at the numbers involved in each of these projects, the two that you have delivered are those that were smaller in quantity than the perhaps more over-ambitious ones. Is that a factor in making a project more deliverable?

Ursula Brennan: I don’t think the volume of order is what made it complex, although one of the things that we are doing at the moment across the whole of the equipment programme is to try, as far as possible, to have a contract that enables us to call off equipment as we need it rather than having to buy in bulk. One of them, the MRAV, was this business about, "Are we going for something light enough that you can fly it somewhere?" It got too heavy, so we thought, "That’s not right". Then, as it turns out, the problems we face in Afghanistan meant that all of us, all nations, have had to up-armour their vehicles. Ironically, it may be that if we had all stuck with MRAV- I don’t know whether that would have been part of the answer.

Q95 Jackie Doyle-Price: Again, you look at this table and at the dates: the project commenced in 1992 and was cancelled in 2001. These projects, on average, all have a 10-year life cycle, which seems to me extremely long.

Ursula Brennan: Indeed.

Q96 Jackie Doyle-Price: I assume that when you started out in 1992, the end date was not anticipated to be that long. What causes the delay? Is it because you are constantly reacting to other budgetary pressures; is it constantly reacting to demand, or is it just incompetence?

Ursula Brennan: We’ve acknowledged that there were a series of things that were a problem, and we are seeking to address them. One was over-elaborate requirements. One was over-complex procurement routes. One was the fact that, because our budget did not balance, we were juggling programmes to make them fit within the budgetary envelope. So a variety of things were wrong and, gradually, we have been tackling each of those.

Q97 Ian Swales: Are we effectively funding research through these periods, potentially for commercial organisations?

Ursula Brennan: We’ve certainly learned from some of the failures and have taken some of the development into other vehicles, but generally we fund research separately rather than through these programmes.

Q98 Jackie Doyle-Price: Can I just quickly ask Lieutenant-General Coward a question? When you are reacting to the requirements in the theatre of war, how quickly can you make a decision to procure a particular vehicle and how quickly is it then deployed?

Lieutenant-General Coward: The best example, probably, was Mastiff 1, which was a combination of Iraq and perhaps ministerial involvement. We delivered vehicles, with the US Marine Corps’s help, in months. We can now deliver similar vehicles in somewhere between months and a year. The most recent example is Foxhound. Having looked at buying something off the shelf and not being able to deliver the levels of protection necessary, we have entered into a development of a vehicle, but it will deliver capability 18 months after signing the contract with the provider.

Q99 Chair: Are you on target with the Foxhound time frame?

Lieutenant-General Coward: Yes, Chair.

Q100 Chair: The Department intends to have the Foxhound available for training for 2011. Is it available?

Lieutenant-General Coward: Yes. They will be off the production line-I hope to be there with our Minister to see them-at the end of the month, and training should start in November [7] .

Q101 Mrs McGuire: You mentioned ministerial involvement that rushed something through. What was the level of ministerial involvement? I mean, they didn’t take out screwdrivers and things like that. What did they do that made a difference?

Lieutenant-General Coward: I was not involved at the time, but anecdotally-

Mrs McGuire: Collective memory is, I think, a better phrase.

Lieutenant-General Coward: Lord Drayson applied energy and focus, and tried to force through decisions that were perhaps having difficulty getting through at the time.

Mrs McGuire: He is a loss to the diplomatic corps.

Q102 Chair: He is a loss. Can I take you to paragraph 4.5 on page 28, where there is a discussion about Mastiff? The end of that paragraph states: "The Department has stated that ‘…a vehicle such as Mastiff, does not come close to meeting the Future Rapid Effect System requirement,’ which is designed to operate across all". Is that true?

Lieutenant-General Coward: Yes, I agree.

Q103 Chair: If that is true, is there money in the budget to ensure that you would do the necessary changes? Is the money there?

Lieutenant-General Coward: I do not think you could convert Mastiff sufficiently to make it deliver to within about 80% or 85% of the utility vehicle requirement.

Q104 Chair: So we are going to dump it, are we?

Lieutenant-General Coward: No. My own view is that we should retain, pro tem, the Mastiffs, and adapt them to a small extent. We don’t have very much money. There is a limit to what you can use them for, but they will provide protected mobility-not manoeuvre, which is what the Army desperately wishes to have, but we will make do with them.

Q105 Chair: What won’t it do? Just explain to a little layperson like me, who doesn’t really get these things, what it won’t do.

Lieutenant-General Coward: With the utility vehicle or with MRAV, we were seeking to be able to manoeuvre across country and in all terrains with a full vehicle load. Mastiff, even in version 3, doesn’t have that level of mobility. It is also not a properly integrated platform.

Q106 Chair: Is there money in the budget to do the repairs and changes required at least to keep it going? Is the money there, yes or no? Yes or no?

Vice-Admiral Lambert: We have a budget, which I’ve asked-

Q107 Chair: Is the money there?

Vice-Admiral Lambert: I have a budget and I’ve asked the Army to give me its priorities as to which equipments it wants to move forward.

Q108 Chair: Mrs Brennan, is the money there?

Ursula Brennan: We don’t allocate the money in that way. We’ve allocated the budget to the Army-

Q109 Chair: In deciding the budget, is the money there to do the job on Mastiff-the changes?

Ursula Brennan: We’re not allocating the money to a single vehicle in that way.

Q110 Chair: But when you set the budget, you think to yourself, "We’ve got to do a, b, c and d."

Ursula Brennan: Indeed.

Q111 Chair: And one of the things that paragraph 4.5 says to me is that Mastiff is not good enough, but we’ve just heard from Gary Coward that actually you’re going to have to spend a bit of money on it to make it serviceable until 2025 or whenever. Is the money there? You must have decided. Yes or no?

Ursula Brennan: No, we haven’t, genuinely. We have not decided because-

Q112 Chair: That sounds so awful to me. When I was a Minister, setting my budgets, I knew what I could afford to do and not do within those budgets. I didn’t pass the buck down the line to somebody else; I took responsibility for those decisions, and I’m sure Anne McGuire felt exactly the same. We wouldn’t have said, "Oh, well, the budget has been cut; it’s down to you what to do," knowing they didn’t have the money to do it.

Ursula Brennan: Can I just be really clear? The armoured fighting vehicles budget covers a whole raft of vehicles: protected mobility, manoeuvre, all sorts of things-

Q113 Chair: You’ve cut the budget from £15 billion [8] -in today’s prices, it probably ought to be £20 billion-to £5.6 billion. Is there money in there to deal with some of the Mastiff problems?

Ursula Brennan: We have not allocated it in that specific way. We have urgent operational requirements vehicles in Afghanistan, we have existing vehicles; we have plans to buy new vehicles; we have announced the intention to proceed with a Warrior upgrade. What we are doing now is saying, "Across that complete range of vehicles, which are the ones that we want to carry on investing in and to make some changes to and bring into core?" Some of these vehicles will be worth investing in; some won’t, so I can’t tell you now that we have put specific money-

Q114 Ian Swales: Do you actually know how much it will cost to do what you want to do with them? Twice, Admiral Lambert has talked about upgradeability. Did you plan for what you were going to do, having spent these billions, with these vehicles afterwards? Is there any plan?

Vice-Admiral Lambert: With the vehicles that we got for Afghanistan, the most important thing was to deliver them as quickly as possible. Time was of the essence, and we traded out a number of capabilities, including upgradeability, that we would have got from something like the utility-

Q115 Ian Swales: So you had no plan as to what you were going to do with them? Do you have a plan now?

Vice-Admiral Lambert: The utility vehicle, as General Coward explained, has a capability to manoeuvre across land so that we can use it within a wider force. But one of the other things that we have learned during the operations in Iraq and Afghanistan is that we can no longer put our soldiers-that’s the infantrymen-in unprotected vehicles. We never had a programme for that [9] , so across the piece we have to look at protection for everybody, from the light infantrymen all the way through to the Mechanised Brigade. We are doing the work at the moment to see whether the urgent operational requirements that we procured are worth bringing into core, because the cost of supporting some of them may be extortionate.

Q116 Chair: General Coward, do you want the money now?

Lieutenant-General Coward: I do need a balance of resource to deal not only with the core programme, but with those UORs that we will take into core.

Chair: Dear, dear, dear. Nick?

Q117 Nick Smith: On page 29 of the Report, it says that "from 2014-15, a significant period of recovery and re-equipment will be required…Without changes to plans for defence spending the likelihood of meeting the Strategic Defence and Security Review aspirations of making ‘…the Army more mobile and more flexible’ appears to be remote until…2025." General Coward, is that good enough?

Lieutenant-General Coward: It is what it is.

Q118 Nick Smith: I thought I would leave that hanging in the air for a while. So you are saying that the Army will not be flexible for a period of about 10 years.

Chair: At least.

Lieutenant-General Coward: It will be less flexible than we had at one stage anticipated.

Vice-Admiral Lambert: In the same way as requirements can be at the cutting edge, the asking capabilities can also be at the cutting edge, and we occasionally have to give them priorities.

Q119 Chair: We have just had an SDSR. You might have thought that, in setting the SDSR, you would have set some figures against it, and we have not done that. That is really the criticism here, which I hope will come out in our conclusions.

Q120 Comptroller and Auditor General: I suppose it is quite a similar question. As we look through the period for bringing all these vehicles in-it is great that the budget is more balanced and that it is getting into balance over a long period-is it not imbalanced, but with a very long time scale for bringing in all these vehicles? Will you not have to compress this rather more for it to be really satisfactory in terms of when these vehicles come into service? If you look at some of them, you are thinking shorter term and yet there are some very long-term in-service dates and that is still in the plan. Are you not going to have a way of drawing some of that back into a shorter time scale?

Lieutenant-General Coward: Surely it is down to the profile of the money that is available, rather than any magic of procurement to shave a few years off a procurement process.

Q121 Comptroller and Auditor General: I quite agree, but if you are making commitments that are not coming into service for such a long time and if you have been saying that you will become a lot more agile, is there any point in planning on something that is going to come into service so far in the future?

Lieutenant-General Coward: It is the best plan that we can have given the resources that are available.

Q122 Austin Mitchell: I have just one question on the armoured vehicle problem. I would have thought that it was fairly basic. Such vehicles are fairly crucial in saving lives against the kind of terrorism that we have had to face in Iraq and Afghanistan, but it seems to have been the fall guy of the system. Paragraph 3.11 on page 22 of the Report states that "the armoured vehicle sector has had the largest amount of funding removed of any individual sector in the five planning rounds conducted between 2005 and 2010" and figure 7 in appendix one shows that-though the impact of the SDSR on combat air is greater-the amount removed from armoured vehicles in the previous planning rounds is still well ahead of everything else.

Why is it that such an important programme, which is so important for preserving the lives of our troops and for delivering them for deployment, is so badly cut? Is that likely to happen again if there are any more cuts in the defence budget?

Ursula Brennan: In terms of taking money out of the defence programme, we have explained that we have had to do that in successive years because the budget was not in balance. We have worked through the SDSR, and in our announcement in July, and we have got it nearly there. It is not quite there yet, but we have it nearly there over 10 years, so we are not expecting to be taking further big bites out of it.

It is always difficult. You can compare and ask what we took out of particular areas, but you can also look at the areas where we actually sought to protect spending. We have been attempting to shift our money more towards things such as ISTAR, enablers, air transport and so on, which are the things where we are particularly short.

It is very difficult to do that when a lot of your budget is already committed, and so it is true that we sometimes have to look at the balance between the spend that is committed and the spend that is uncommitted. In doing so, however, we are guided by Admiral Lambert’s team, which looks at the capabilities that we require to be able to deliver and which shows the areas where we can take more risks. Our aim is to get to a point where we have a balanced budget and where we do not have to make those judgments.

Q123 Chair: Okay. We know all that. I am just trying to draw us to a close. Anne wants to come in. Do you agree with recommendation "b" on page 10 of the Report, which says that you should report to Parliament where gaps in the structure and capabilities arise as a consequence of resource management decisions?

Ursula Brennan: We are concerned about the notion of reporting gaps in capabilities-about where the gaps are-that would actually give comfort to our enemies.

Q124 Chair: As a consequence of resource management decisions.

Ursula Brennan: Even if they were as a consequence of resource management decisions, we don’t really want to publish something that says, "This is where you can come and get us because we’ve got gaps." We need to think about how we would respond to that. We try to avoid publishing things that say, "This is where our staff are not very well trained," or, "This is where our equipment isn’t very good," because it is just an invitation to people to attack us in those areas.

Q125 Mrs McGuire: There is a bit of a divide here between what is a balanced budget and what is good, effective procurement. The issue of a balanced budget is probably for political discussion rather than for discussion here. As for whether or not the budget is actually the right size: you can balance a budget that is tiny in the same way that you can balance a budget that is large.

In the closing minutes, I want to look at the relationship between the MOD and the defence industries. We place a great deal of emphasis on your effectiveness and efficiency in negotiating contracts. Can I ask what engagement there has been with the defence industries, in terms of the new environment? I will not use the word that Vice-Admiral Lambert does not like.

We are going for more off-the-shelf solutions. What discussions have there been with the industry? What has been its response? Has any assessment been made of the wider economic implications of withdrawing some of those issues relating to research and development, which might perhaps have been part of the partnership in the procurement process? I appreciate that there are three or four questions there.

Vice-Admiral Lambert: There is no doubt in industry’s mind that we are heading towards more procurement off the shelf, that we are looking at making sure that we understand fully the cost drivers behind the programmes and that we need to ensure that we can upgrade all our programmes.

Q126 Mrs McGuire: Does "off the shelf" mean off the shelf inside the UK, or with the USA, South America or eastern European countries? What exactly does that mean?

Vice-Admiral Lambert: I believe that international competition is the route that will give us best value for money. As far as dialogue with industry, that is done at Abbey Wood. I don’t know if General Coward would like to comment.

Lieutenant-General Coward: There has been a long dialogue with industry that goes back before the defence industrial strategy, where we made a judgment that for this sector, as Admiral Lambert said, best value for money was through international competition, although we do require the ability to maintain, modify and upgrade our vehicles onshore. So, generally, industry teams with someone else. On the Scout programme, GD took a Spanish-Austrian product, brought it onshore and will modify it for use by the UK. With the utility vehicle, three competitors looked at international platforms, but they had onshore capability to deliver, maintain, upgrade, and so on.

Most of industry understands the direction of travel and companies such as BAE Systems, Lockheed Martin and GD UK are beginning to shift. They are beginning to look towards maintaining and upgrading those vehicles to maintain their core engineering capability and a degree of production. But production is largely build-to-print and assembly rather than the very sophisticated cradle-to-grave production that we may have had in the ’50s and ’60s.

Q127 Mrs McGuire: Does that give you any concern about future security of supply for our service personnel? Are you concerned about how we would be able to respond as a country as part of a larger alliance, be it NATO or the EU?

Lieutenant-General Coward: That is a concern, but with our arrangements, and by focusing on upgrade and modifications, we retain sufficient expertise onshore to deliver what we require, either routinely or in a time of crisis.

Q128 Mrs McGuire: Do you share that view, Vice-Admiral?

Vice-Admiral Lambert: I do not share the concern. Most, if not all, of the urgent operational requirement vehicles have come from overseas, and they have delivered to time and provided what we require.

Q129 Chair: But throughout their life they might be more expensive, because of the service, spares, logistics and so on.

Ursula Brennan: Depending on what we did with them, yes.

Chair: We would enjoy continuing this session, but there is a debate in the Chamber that is of some importance to Committee members, so we will terminate. Thank you for much clearer evidence this afternoon.


[1] In 2005 the MoD planned to spend £4 billion on Armoured Vehicles over the next 10 years, not £14 billion.

[2] Cpl Sarah Bryant was killed alongside LCpl Reeve, LCpl Larkin and Pte Stout on 17 June 2008.

[3] Under current plans, the first of the new Chinooks will enter service with the RAF in May 2014, while 3 aircraft will be available for deployment with trained crews and all necessary support in January 2015.

[4] Total number of Crown Servants working on AFVs in Abbey Wood is 365

[5] Total spend on TRACER was £131 million not £700 million.

[6] No-One has died in a Cougar-based platform (Mastiff, ridgeback and Wolfhound) or in Husky as a result of enemy action.

[7] Foxhound will be off the production line in November, and training is due to start in December.

[8] In 2005 the MoD planned to spend £4 billion on Armoured Vehicles over the next 10 years, not £15 billion.

[9] Vector Protected Patrol Vehicles (PPV) and upgrades to Snatch vehicles were delivered through core programmes. The Medium PPV programme (Vector replacement in –service 2018) was cancelled in the SDSR.