The Warm Front Scheme - Public Accounts Committee Contents


2  Contract management

10. The Department for Environment, Food and Rural Affairs contracted out the management of the Scheme to eaga plc in 2005. Since letting the contract, the Scheme has changed from a relatively small contract into a major programme. Government funding has increased significantly and by 2010-11 some £1,811 million will have been invested in the Scheme (Figure 3). The Department for Environment, Food and Rural Affairs established a Warm Front Scheme board which includes representatives from consumer organisations and eaga plc to oversee the contract and financial performance. Three changes were made to the contract in 2006, but it did not appoint a manager to oversee day to day performance until the summer of 2007.[14]

Figure 3: Scheme funding, 2005-06 to 2010-2011

Source: C&AG's Report, Figure 3

11. The absence of day to day professional oversight of the Scheme has led to difficulties in contract management. For example:

  • The contract between the Department and eaga plc includes a profit share arrangement, where any profits over 11% are shared equally between the two parties. In April 2008, incorrect profit calculations in the 2006 and 2007 cost certificates were identified, which resulted in eaga plc paying back £652,000 to the Department for Environment, Food and Rural Affairs.[15]
  • eaga plc owned subsidiaries can carry out up to 30% of installation work under the Scheme. The Department has recently reviewed the clause because of confusion between the two parties as to whether the limit related to the value of work or number of jobs, or whether the percentage is measured each year or over the lifetime of the contract. It has been determined that the clause relates to the value of the work undertaken. In 2007-08, work by eaga's subsidiaries accounted for 30% of the overall value of work and 31% of all jobs completed.[16]
  • The profit share arrangement does not include any profits generated by eaga's seven subsidiaries for other work undertaken in relation to the Scheme, for which eaga group received £95 million in income in 2007-08.[17]
  • As part of its original tender, eaga plc had noted that transferring the contracts for the supply of heating materials from the Department to the contractor would attract a lower VAT rate of 5%, resulting in annual savings to the Scheme of over £5 million a year.[18]

12. The cost of works is a common complaint about the Scheme. Under current Scheme rules, customers are unable to obtain alternative quotes or use their own contractors. Only contractors on the eaga panel of contractors are able to undertake work. The National Audit Office undertook a cost comparison for seven of the most common installation works undertaken by the Scheme and found that prices charged by the Scheme were competitive compared to industry averages (Figure 4). Gas and oil boiler replacements were at the top end of the range of costs modelled. The boiler of choice on the Scheme is an Ideal boiler, although the qualified engineer may determine that another boiler is more appropriate in some circumstances. The boilers are procured from Wolsley Plc through Plumb Centre under a five year contract and eaga does not make any profit on the cost of the actual boiler. In 2009, the Department and eaga were in mid-contract negotiations, including about the scope to secure cost savings in the supply of materials.[19]

Figure 4: Cost comparison of Scheme measures

Note: All figures exclude VAT. The Building Research Establishment (BRE) model is based on four dwelling types chosen to represent the target group for the Scheme: two-bedroom mid terrace house, 3-bedroom semi detached house, 3-bedroom detached bungalow and 2-bedroom low rise top floor flat. The price ranges reflect estimated costs for work on these types of dwelling, adjusted to reflect regional differences in the costs of works.

Source: C&AG's Report, Figure 14


14   Q 13; C&AG's Report, paras 1.8, 1.11, 4.2-4.3 Back

15   Q 105; C&AG's Report, paras 4.7-4.8 Back

16   Qq 84-85; C&AG's Report, para 3.8 Back

17   Qq 17, 104; C&AG's Report, para 4.7 Back

18   C&AG's Report, para 4.4 Back

19   Qq 88, 90, 95, 109-117; C&AG's Report, paras 3.1, 3.10 Back


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2009
Prepared 24 July 2009