Select Committee on Welsh Affairs Minutes of Evidence


Examination of Witnesses (Questions 780-799)

MR RICHARD WAITE AND DR BRIAN BURNETT

17 MAY 2006

  Q780  Albert Owen: Do you see any potential conflict between the owners of the site and them not getting involved in certain aspects of it?

  Dr Burnett: There is a potential for conflict but the contract is set in such a way and the protocols are agreed with the regulators in such a way to ensure that does not happen. It is something that we constantly remind ourselves of because we are not the licence holder. They are a full scope contractor which means that they provide the programme of works, we provide the money and there is an incentive arrangement in the contract whereby they earn a fee against performance against a contract of work that they have put forward and we co-ordinate in a national sense. It is a very important area that we do not direct work that we are not licensed for.

  Q781  Albert Owen: At present, what is the timetable for decommissioning Wylfa? You have just brought out this strategic plan, of which we have had the draft and the final. What is the timetable if it can be broken down into layperson's terms?

  Dr Burnett: We will generate until 2010 and there then follows a period whereby we remove the fuel which takes between 18 months and two years, so that takes us to about 2012. Then there is a period of preparation for care and maintenance where all of the facilities outside of the actual reactor core itself are stripped away and that takes us until 2025. The care and maintenance then continues from that date until final site clearance in about 2116. In that period you then come back and remove the core and its contents. That is the established plan reflected in our strategy.

  Q782  Albert Owen: There has been some movement since your draft. You are a new body but you did say this would be some 250 years in total. Is 2116 still the end date or can that be brought forward?

  Mr Waite: Shall I comment on that? One of the issues that we identified in our strategy was that we wanted to examine the acceleration of final site clearance and, indeed, we do have the commitment in our strategy now to create a business case by the end of this financial year site by site to see whether we can bring forward those end dates. We believe that final site-by- site clearance of that and all areas in the future gives us a number of difficulties in terms of maintenance of skills, socio-economic issues and intergenerational equity issues, and it would be far better if we could see a way to clear them earlier. We have talked about a so-called 25 year site clearance plan but that is a nominal figure. We are investigating during the course of this year what we can do on a station-by-station basis and we will create a business case to present to the DTI if we believe we can do it earlier.

  Q783  Albert Owen: I presume you have been learning from sites such as Trawsfynydd?

  Mr Waite: We are. We are learning not only from our UK experience but we have recently agreed some collaboration arrangements with EDF who have got some gas cooled operating stations that they have got advanced plans for as well and they are looking to clear their sites within circa 25 years. We are learning internationally as well as from the UK environment.

  Q784  Albert Owen: Just one final question on this. During that timetable, and I know you have already engaged with the local community, what further issues do you need to discuss with them? For instance, the socio-economy issues are important and you were talking about retraining programmes already engaged on site but I am interested in outside, so what is your relationship with the local community?

  Dr Burnett: We picked up the brief in April of this year. One of the first things we sought to do was to find a socio-economic baseline so we joined together with Anglesey County Council, the Welsh Development Agency and Anglesey Aluminium to do a baseline study for the island. We have done that. We did a public presentation of that. The results of that report will be publicly available. We regard that as a baseline for all of those bodies and any other bodies that are interested for the way forward. We now seek to work with the relevant bodies to look for opportunities to deal with the socio-economic issues from running down station staff. We still have some time to do that and a window of opportunity. We look for capital investment; we look for sustainable things to contribute towards. Over the next two years, I guess things will come forward and we will continue to develop that. The site contractor is a full scope contractor. Part of their contract is to develop these links and to look for opportunities for socio-economic investment.

  Q785  Mark Williams: Have you any clear estimation for the costs of decommissioning, particularly in the Welsh context, Trawsfynydd and Wylfa? The latest figure UK-wide this year was 62.7 billion. In a Welsh context, where are we in your estimates?

  Dr Burnett: The Wylfa whole lifetime costs are 1.7 billion. I am not sure of the Trawsfynydd figure but I would have thought it was of the order of three-quarters of a billion.

  Q786  Nia Griffith: Turning to Sellafield, perhaps you can explain what sort of waste Sellafield receives?

  Mr Waite: If I can explain the process in broader terms, the fuel that the Magnox stations use gets manufactured in Springfields at a Magnox fuel manufacturing facility there. We might go on to say a little more about the implications of that in a minute or two. That fuel then gets transported to the Magnox stations, Wylfa included, where it is loaded and the Magnox station at Wylfa has something like 600 tonnes of fuel per core. Progressively, as that fuel gets burned up, it gets taken out and sent by rail transport in very heavily protected flasks up to Sellafield at about a rate of 140 tonnes a year on a replenishment basis. The fuel goes in; the fuel goes out, so it is not waste at that point. It is spent nuclear fuel. When it arrives into Sellafield it goes into a series of facilities, the first of which is cooling ponds where it sits for a number of months to cool off, before it is then decanned. The fuel is decanned of its magnesium alloy coating, just revealing the uranium metal fuel, which is ultimately put into a magazine and transferred into a nitric acid dissolution process inside the Sellafield complex, inside a building called B205. This particular building is the Magnox reprocessing facility in Sellafield. It is more than 40 years old. It was commissioned and up and running in 1964. It has been dealing with all of the Magnox fuel from all of the Magnox stations and indeed has dealt with it very well up until this point. What happens in that particular building is the fuel is dissolved. Plutonium and uranium are extracted and turned into oxide powders for safe storage in Sellafield. The remaining fission products are then concentrated down during a series of evaporation processes and ultimately stored as heat generating high level waste inside the Sellafield complex prior to being taken into a vitrified cask, which is the long term storage and disposal concept that has been in place for some time now for dealing with high level waste. The whole cycle takes the fuel through from being fuel to dissociated plutonium, uranium and high level waste in that sense. That then gets turned into the glass blocks which ultimately will get disposed of or stored, depending on the government's agreement with the CoWRM recommendations which are coming along in the summer, as we know.

  Q787  Nia Griffith: What happens currently with it once you have it in vitrified form?

  Mr Waite: It is stored. There is a vitrified product store in Sellafield where the glass blocks are effectively encased in stainless steel and the stainless steel canisters are stacked up on top of each other in a series of cells and stored there until such time as we decide collectively in the UK what we are going to do with them, which could be longer term storage still or ultimate disposal in some kind of repository. Obviously, that is where CoWRM are potentially heading.

  Q788  Nia Griffith: What sort of timescale do they need to be stored for?

  Mr Waite: There is a cooling period in Sellafield. I cannot remember the exact numbers but it is of the order of a small number of years, from memory, before you can start shipping it out. It is effectively cooled to be able to be handled and put into a repository. I cannot remember the exact number but it is not weeks or days. It is certainly more than that.

  Q789  Nia Griffith: There have been some leaks of the CoWRM report which was supposed to be coming out in July. What would you see as potentially the most logical way to store things in the long term?

  Mr Waite: During the CoWRM public consultation period last year we offered our views in that we would like to see some form of deep geological repository as a final resting place for this high level waste, primarily because that is where all the best practice seems to be heading. The Finns and so on are heading in that direction. Also, it gives a geological barrier to the fission product release and so on and we believe a safety case can be created to protect the environment for the time required. We made those recommendations to CoWRM. CoWRM, as you probably already know, have released their draft report. It came out a week or so back. It suggested that that is what they are going to recommend but their formal recommendations will not come out until the summer. If they do recommend deep geological disposal, we would welcome that. The key issue for us thereafter is the timing and availability of that repository because clearly the storage regime we have in place at the moment is linked to how long the material has to be stored vis a vis the availability of the repository.

  Q790  Nia Griffith: Are there any suggestions as to where that might be?

  Mr Waite: It is far too early. It would be premature to speculate. We do not even know what the process will be for site selection because I do not think anybody has designed it yet. I believe the government has to decide upon the CoWRM recommendations in the summer before any of that is considered so I see it as very premature to be even thinking about sites.

  Q791  Nia Griffith: You mentioned about 140 tonnes per year coming to you from Wylfa. Is that a correct figure?

  Mr Waite: It is the average number. The fuel that has been sent to Sellafield since 1971 from Wylfa is around 5,000 tonnes. If you divide the time between 1971 and now, it comes out at about 140 tonnes a year on average.

  Q792  Nia Griffith: That is currently all still stored at Sellafield?

  Mr Waite: No. The vast majority of that has been reprocessed, the plutonium separated, the uranium separated and the high level waste vitrified as a result. That is an ongoing process. The vitrification process does not finish in Sellafield until 2015. That is the current target and we will stop vitrification at that time.

  Q793  Nia Griffith: Of the 140 tonnes that you get, you say you vitrify some parts of it. What percentage of the volume is that and what happens to the rest?

  Mr Waite: It is a very small percentage of high level waste. It is of the order of less than 2% from memory. The vast majority is recovered uranium because this is uranium metal fuel. The main construct of that is uranium 238 and that 238 is recovered during the dissolution process. It is separated out from the dissolved liquor and it is transformed into powder form for storage in drums for potential disposal or potential reuse. That is another strategic issue that we have identified in our strategy document that we are currently working on, the issue of whether separated, recovered uranium is for reuse or for disposal.

  Q794  Nia Griffith: What volume do you receive from all of the nuclear power stations?

  Mr Waite: I do not have that at my fingertips.

  Dr Burnett: The plant at Sellafield reprocesses around 800 to 1,000 tonnes a year, if that is helpful.

  Q795  Nia Griffith: Can you tell us a little bit about the life span of Sellafield? Is it going to go on for ever? Does it have a life span and is there a proposed last date for receiving waste?

  Mr Waite: Yes, there is. The current plan for closure of the Magnox reprocessing facility is linked to the time it will take after closure to decommission that plant, clean it up to meet the overall commitments that have been entered into by the UK, to meet the OSPAR Convention requirements for near to zero radioactive discharges into the north east Atlantic by 2020. When you work back from 2020, you come up with a date whereby you have to effectively stop operations. Otherwise, you do not have enough time to diminish the discharges. That current date for B205, the Magnox reprocessing facility, is around 2012/2013, which then drives back into the two years that Brian mentioned in terms of the flow of fuel from Wylfa needing to come at around 2010. You can see from 2010 to 2012 and through to 2020 there is a programme of activities all linked together to ensure that those discharge requirements are met. As I said earlier, the plant is an ageing plant. There are increasing burdens on asset care and maintenance that are quite significant. Any potential extension of that plant, setting aside the regulatory commitments and so on and the international commitments to reduce discharges, would be quite expensive and also burdened with some risk.

  Q796  Nia Griffith: You say it would be very problematic to extend the timetable if Wylfa was given an extension. Are you saying it would be problematic to be continuing to receive waste from them after 2010?

  Mr Waite: Yes, very.

  Q797  Nia Griffith: You cannot see an easy way of extending it?

  Mr Waite: There is no easy way. It is not just Sellafield. Sellafield is the primary problem but there are other problems with extensions which we can discuss if you wish but Sellafield's problem is those facilities which are ageing, our need to decommission them and clean them up to meet the various international commitments that we have. That drives our current timescale, coupled with the fact that they are ageing and taking some looking after in terms of the costs and associated activity of keeping them maintained.

  Q798  Nia Griffith: Looking to the future, if there were a new generation of nuclear power stations, would you say there would also have to be a completely new generation of dealing with the waste? In other words, new facilities completely?

  Mr Waite: New build, as I am sure you are aware, is not our domain. In terms of the decommissioning or waste side of it, it is not necessarily the case that you have to reprocess fuel. Other countries and we have a concept where you can store the fuel until you have decay and heat drop-off to the point where you can consider direct disposal in a repository. That is the assumption, for example, for some of the plants in the UK, the more modern plants, that the fuel will not be reprocessed so you do not need a Sellafield type facility in terms of reprocessing. What you will need is a store to store the fuel until such time as you decide that you are going to dispose of it. There are options around fuel disposal or fuel handling that do not necessarily mean reprocessing would have to be continued or replaced.

  Q799  Nia Griffith: If you do not reprocess, does that mean that you have to store for longer?

  Mr Waite: It depends on how long it takes to put the repository together so the repository availability timescale is crucial in that. Again, there is a timescale whereby the fuel has to be stored to allow it to decay and cool off. It is in the order of years to allow it to be handled or packaged. You would have to build a plant to condition it; you would have to have containers to put it in and so on. You would have to store those containers and then those would need to be disposed of in due course. That is indeed our plan for some of the later arisings from advanced cooled reactors. At the moment that fuel will be stored and directly disposed of in due course.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries index

© Parliamentary copyright 2006
Prepared 20 July 2006