Select Committee on Public Accounts Minutes of Evidence


Examination of Witnesses (Questions 80 - 99)

MONDAY 1 MARCH 1999

SIR ALAN LANGLANDS and MR TIM MATTHEWS

Jane Griffiths

  80.  Looking at paragraph 2.13 of the Report, there was a number of space increases on the project, basically more things were added to the project and that was on a constraint side. So inevitably that took the cost up in real terms by 80 per cent. That being so, does that not mean that the original approval in principle lapsed because the approval in principle was based on much lower costs?
  (Sir Alan Langlands)  It did lapse.

  81.  Therefore why was it agreed?
  (Sir Alan Langlands)  Sorry, it was agreed and then it lapsed. It was not followed through to the next stage.

  82.  The whole project carried on with those increased costs. I am trying to get here where the accountability was, where the checks were on the escalating costs?
  (Sir Alan Langlands)  The planning work continued and, as I have said earlier, several times, I do not think the original cost estimate of £35.5 million was realistic. Planning work continued and as outlined here that planning work threw up higher costs associated with the nature of the site, the specialist nature of some of the services that were going to be accommodated in the site and the size of the site. There is particular reference here made to the increases stimulated by the involvement of the medical school for teaching purposes.

  83.  You said earlier, Sir Alan, that you did not believe that there was any sense of realism in this project until 1994?
  (Sir Alan Langlands)  No, I did not say that. I said that I think there was increasing realism from 1989 onwards. I think the real management grip of this project started in April 1993. The first time I think we had a realistic estimate of costs was around the summer of 1994.

  84.  How can this Committee be assured that kind of lack of accountability and lack of realism in cost assessment will not recur?
  (Sir Alan Langlands)  I think, as we have discussed this evening, our guidance on these issues is much clearer, much starker than it has ever been. The line of accountability which was muddled, goodness me—we have to have very complicated diagrams to set out what it is in this report—is no longer muddled. The project owner is the chief executive of the Trust, the accounting officer is me, and we are the key people to be held accountable for the delivery of these projects to cost and to time. We monitor across all the dimensions of these projects, each one of them, once a quarter.

  85.  Okay. This project began at a time of organisational disruption when the NHS was being reorganised. I suspect that the NHS may well continue to change in the way it is organised, in fact I think it would be rather bad if it never changed again. It seems to me that there is inevitably going to be organisational change and there will be future projects and this project which began at a time of organisational change has brought about uncontrolled cost escalations. How can we be sure that will not happen?
  (Sir Alan Langlands)  First of all, the organisational change at this time was very widespread. Regions were being abolished, district health authorities were taking on new roles, trusts were taking on completely new dynamics. Certainly for the foreseeable future, as far as I can see ahead for the next five years, I do not think we are going to experience organisational change on that scale at all. Trusts will be the key players in relation to capital investment. The chief executive of the Trust will be the key accountable person. It is possible that these people will change for some reason or another. I think the lesson that we discussed earlier is the importance of ensuring that the project sponsorer, the project management of these things, is consistent throughout the life of the project and that is certainly something that we strive for now and clearly was not being done effectively at that time.

  86.  It is going to be more effective. Looking back at the original brief for the approval in principle which was drawn up by planning consultants at a very early stage, yes?
  (Sir Alan Langlands)  Yes.

  87.  That was done rather quickly, was it not?
  (Sir Alan Langlands)  It was done very, very quickly.

  88.  Why was it done so quickly?
  (Sir Alan Langlands)  I do not know.

  89.  It seems rather rash to have done it so hastily for a project of this size?
  (Sir Alan Langlands)  Well the possibility I guess is the point that I discussed with Mr Williams earlier, or he discussed with me, that this was a group of people who had a plan for the development of the services on their patch and they wanted to put a marker down, they wanted to try and force their way into the queue for capital investment. The result was this rather quick and dirty approval in principle.

  90.  That is a possibility, you do not actually know whether that was what happened. It seems to you to be a possibility?
  (Sir Alan Langlands)  I think that is the most likely explanation. I do not know the details.

  91.  Looking at figure 13 of the Report. The variations to the brief were introduced which took the costs up by nine million approximately at that time. It seems to me that the client wanted the project to go ahead almost regardless of what the costs were and whether or not there was a plan for accountability. It is as if that was not taken into account when variations were introduced, is that right?
  (Sir Alan Langlands)  Certainly it would be the case that the client wanted the project to go ahead. There was no doubt about that, that would be their motivation. Some of these increases, the sort of things that are set out in figure 13 are really very important. Probably there are variations there in relation to so-called statutory requirements. There may have been changes, for example, in fire precautions that needed to be taken into the brief. There was the service change that we discussed earlier, nearly three quarters of a million pounds in relation to the Asthma and Allergy services. I think there was a combination of slack practice, legitimate variations and some late interventions from the client on the design of this project. All three of these things began to inflate the cost which takes us back to the issue of when in a project as complicated as this the design should be frozen.

The Committee suspended from 17.40 to 17.56 for a division in the House

Jane Griffiths

  92.  In February 1991 who authorised the region and the trustees to proceed with Stage 2 of the management contract?
  (Sir Alan Langlands)  No one authorised them to proceed because they did not come back to the Department for authorisation. The basis of the financing at that time had been agreed and had taken account of the points I made earlier about the VAT and the tenders for the Stage 2 works. So it was seen as a continuation of the management contract and whilst the Department would have been aware that it was going on, as I understand it looking from this distance, there was no attempt to come back for an approval and certainly no attempt to seek further financial approvals from the Treasury.

  93.  Not much more than a year later in May 1992 NHS Estates urged the management executive to clarify outstanding funding issues, did they not?
  (Sir Alan Langlands)  Yes, that is right.

  94.  What happened? It is not clear to me whether those outstanding funding issues were clarified or if they were they are not approved.
  (Sir Alan Langlands)  In a sense that was the beginning of a chain of events that began to look at the likelihood that the Stage 2 budget costs, which were £118 million, would not have been sustainable so that people were uncovering at that time the issue in relation to asthma, they were uncovering the beginnings of the tensions between Austen's and Kentz, they were beginning to understand some of the conflict between the anxiety about some of the contractors and it was essentially that work from April 1993 that Mr Matthews and his team began to pick up and ask questions. So there was a growing understanding that there were problems here and an absolute imperative on the new trust coming into place from April 1993 was that they had to grip these problems and that led to their work with Davis Langdon and Everest to really have the first proper review of what had been going on, how the cost increases could be attributed across the various headings that we have been discussing today. So NHS Estates' intervention did not have an immediate impact but it did raise awareness that this scheme was out of control and needed to be gripped and that was very much the tone of things when the new trust came into place.

  95.  Just in time because there had been a number of years where there had been chaotic management control which resulted, did it not, in the project being completed three years and four months late and £67 million over budget in 1997?
  (Sir Alan Langlands)  Yes.

  96.  In my constituency in Reading we have got a new hospital project there which we have been waiting for for a long time budgeted for about £75 million. I hope, and I am not sure, that none of the people that were involved in this one are going to be involved in that one because one of the things I need to reassure my constituents is that nothing of the sort will happen with this project. Do you think I can?
  (Sir Alan Langlands)  Yes.

Jane Griffiths:  Thank you Chairman.

Chairman:  Geraint Davies? Happy St David's Day, by the way!

Mr Davies

  97.  You will notice that I am wearing a genetically modified daffodil; they last longer and smell less. But I am a London MP from Croydon and I am very very concerned about the misuse of resources in this case. You seem to suggest that the real start date of this project was 1989 on the grounds of bureaucratic structural changes in health, namely the shift from regional health authorities to trusts. Do you think it is a legitimate excuse for this waste of money that someone like you can come along to this Committee and say that was when we were changing from regions to trusts and will you be giving similar explanations when there is other reform of the Health Service as there is now?
  (Sir Alan Langlands)  I was not suggesting cause and effect. I was merely observing that there was a lot of organisational change and I think that did lead to changes in personnel at key points. No, I have no intentions of coming back and arguing that. As Jane Griffiths has said, where there is the likelihood of organisational change in the future I do not think it will be so radical but where it does exist we must try in these schemes to achieve two things, constancy of purpose and continuity of key personnel. That is our objective.

  98.  So it is not legitimate for gross mismanagement to be hidden behind structural change in the Health Service—because that is what you seem to be saying? As a person who was a regional general manager, I noted from your CV, I wonder whether you have got similar appalling experiences in your former role and that you are introducing a defence that everything is changing so no one can manage anything properly?
  (Sir Alan Langlands)  No, certainly not. I was a regional general manager for a short time, as Mr Page would remember if he were still here. I did have the pleasure of inheriting the Chelsea and Westminster problem when I went to North West Thames Region and just as we have done in this one eventually sorting it out, but I do not take pleasure in either of these things. The point is that we have got all these things on a proper footing and our management of these things is much better than it was through the 1980s and the early part of the 1990s.

  99.  In the conclusions of the internal studies as to why there was this appalling escalation in costs and therefore this imperfect allocation of resources, some of the reasons given were lack of control of the design team variations, changing client brief, etcetera, etcetera. Would you agree that those are not particularly profound conclusions given that the management of the project sponsorship, as it is called, was in fact changed four times and inevitably that led to four different perspectives and egos of these people who were paid £1.5 million it says in the account as directors' salaries. It would be inevitable that every time they changed one of these people they would change the brief and add on millions of pounds to the public cost for prevarication or the change of direction.
  (Sir Alan Langlands)  I do not know, I have never tried, but I would be very surprised if we could link specific design changes to specific individuals. I do not under-estimate the point about the disruption because of changes of staff and I do think that probably led to weaknesses in control.


 
previous page contents next page

House of Commons home page Parliament home page House of Lords home page search page enquiries

© Parliamentary copyright 1999
Prepared 2 September 1999